Judgement No. 91-1204C
(Filed:
February 20, 1998)
* * * * * * * * * * * * * * * * * * * * * * * * * *
* |
* |
|
|
* |
|
McDONNELL DOUGLAS
CORPORATION |
* |
|
AND GENERAL DYNAMICS
CORPORATION, |
* |
|
|
* |
Termination for
Convenience |
Plaintiffs, |
* |
Settlement Claim; Incurred |
v. |
* |
Costs; FAR Part 31;
FAR |
UNITED STATES OF AMERICA, |
* |
Part 49; Allowability; |
|
* |
Reasonableness;
Allocability. |
Defendant. |
* |
|
|
* |
|
* * * * * * * * * * * * * * * * * * * * * * * * * *
* |
* |
|
Caryl A. Potter, III, Elizabeth A. Ferrell, and Roger
K. Heidenreich, Sonnenschein Nath & Rosenthal, Washington, D.C. and St.
Louis, Missouri, for plaintiff McDonnell Douglas Corporation, with whom was John
W. Walbran, McDonnell Douglas Corporation, of counsel; Herbert L.
Fenster and David A. Churchill, McKenna & Cuneo, Washington,
D.C., for plaintiff General Dynamics Corporation.
Bryant G. Snee, United States Department of
Justice, Washington, D.C., for defendant, with whom was George P. Williams,
Office of the General Counsel, Department of the Navy, of counsel.
OPINION AND ORDER
HODGES, Judge.
INTRODUCTION
Plaintiffs McDonnell
Douglas and General Dynamics entered into a full-scale engineering and
development (FSED) contract with the Navy in 1988 to develop the A-12, a Stealth
aircraft. The Navy terminated the contract for default in 1991. We ruled that
the termination for default was improper and converted it into a termination
for the convenience of the Government. See McDonnell Douglas Corp. v. United
States, 35 Fed. Cl. 358 (1996). The purpose of this opinion is to set forth
our reasons for awarding plaintiffs most of the costs that they incurred in
performing the A-12 contract.
BACKGROUND
"[I]f, after
termination, it is determined that the Contractor was not in default, or that
the default was excusable, the rights and obligations of the parties shall be
the same as if the termination had been issued for the convenience of the
Government." Federal Acquisition Regulation (FAR) 52.249-9(g). We approach
this situation as if the Government had terminated this contract for
convenience on January 7, 1991 -- the date of the default termination.(1)
Plaintiffs argued that the
FAR entitles them to incurred costs plus a reasonable profit, while defendant
urged us to adjust plaintiffs' cost reimbursement amount downward to reflect
the loss that they would have sustained had the contract been completed. When
the Government terminates a contract for its convenience, the contractor
"should be compensated fairly for the work done and the preparations made
for the terminated portions of the contract, including a reasonable amount for
profit." FAR 49.201. Typically, the contractor is entitled to recover all of
its incurred costs and settlement costs, and reasonable profits if warranted. See
FAR 52.249-2(f). If it appears that the contractor would have suffered a loss
on the entire contract, however, the contractor would not obtain a profit, and
its cost recovery is reduced according to the rate of loss. See id; see
also McDonnell Douglas Corp. v. United States, 37 Fed. Cl. 270, 272-73
(1996). For reasons stated in a December 1996 ruling, however, we did
not allow profit or consider to what extent a loss ratio might apply. See
McDonnell Douglas Corp., 37 Fed. Cl. at 272. We could not consider
plaintiffs' Requests for Equitable Adjustment for similar reasons. See Id. at
272. During trial in June and July 1997, we considered only the costs
plaintiffs incurred by performing the A-12 FSED contract, Lots I, and II
options, and "wind-up" termination costs.
Plaintiffs presented a
termination for convenience claim for $3.992 billion, excluding profit and
interest and before application of the "funding cap."(2) The $3.992 billion in costs
include: $3.750 billion for the FSED portion of the contract, $.212 billion for
Lot I, and $.030 billion for Lot II.(3) Plaintiffs submitted their
certified termination for convenience claim on a total cost basis in June 1991.
Later updates covered costs incurred in the interim, such as subcontractor
settlements.
The funding cap imposed by
the court limits recovery to $3,499,793,515 for the FSED portion of the
contract. Additional funds obligated through the Incentive Price Revision and
Economic Price Adjustment clauses raise the funding cap to $3,635,767,376.
Adding to this amount the $.212 billion for Lot I and $.030 billion for Lot II,
which are undisputed amounts "outside" of the cap, we arrive at
$3,877,767,376, the highest award possible with the funding cap in place.
Unless the Government's valid challenges would bring the amount claimed by
plaintiffs below this figure, findings detailed below have little practical
effect.
The parties asked us to
determine plaintiffs' total incurred costs, irrespective of the cap. If the
funding cap is higher or does not apply, plaintiffs' reasonable, allowable, and
allocable costs total $3,978,002,676. Otherwise, plaintiffs may recover no more
than $3,877,767,376 plus statutory interest. That is the amount for which we
enter judgment today.
Problems with the Coopers
& Lybrand (Miller) Report
The Government hired
Coopers & Lybrand to audit plaintiffs' incurred costs. This effort was
managed by Frederic R. Miller, an auditor who was the Government's only witness
at trial.
The Government's challenges
to plaintiffs' claimed costs are based entirely upon the Miller Report.
Plaintiffs supplied proof with respect to all of their claimed costs to some
degree, but more in some areas than in others. Some of these costs could not be
awarded if strict accounting standards were employed. We believe that the FAR
does not limit such costs to a rigid application of cost accounting standards.
Plaintiffs attacked Mr.
Miller's experience and credibility along with the usefulness of his report.
General Dynamics contended that Miller had no personal knowledge and experience
with the program. He was "denied access to the very government personnel
who were familiar with it," such as the program manager, contracting
officer and class desk. Additionally,Miller had no experience working for an
aircraft design company and no prior experience with an RDT&E program that
had been terminated. Miller had only a general sense of what the A-12 contract
required; he did not have the necessary security clearances to know what it
specifically required. Miller lacked familiarity with the requirements,
schedule, and terminology of the A-12 research and development contract,
including such issues as concept formulation, DEM/VAL, IDR, PDR, CDR,
concurrency, how many radars were required, how many test aircraft were
required, how many change orders occurred, when first flight was, and when and
how the contract schedule changed. Despite this inexperience, [Coopers &
Lybrand] consulted with no one in the Navy who had been involved with the A-12
program for technical assistance -- not Captain Elberfeld, not Captain Cook,
not Mr. Mutty, and not Admiral Morris. Miller conceded that such information
could be competent evidence for an auditor to consider, but observed that he
did not have access to such people. . . . Indeed, the government instructed
C&L not to consult with such Navy personnel.
Plaintiffs' problems with
Miller's report do not stop there. General Dynamics questions, inter alia,
Miller's level of experience/familiarity with the "25% rule" that
applies to items being returned to vendors for restocking, Inventory
Verification Reports, and plant clearance officers. According to General
Dynamics, Miller "did not consider relevant FAR and DCAA Contract Audit
Manual ... provisions before questioning plaintiffs' post-termination relocation
expenses."
Miller's report claims to
represent the "independent and objective opinions of [Coopers &
Lybrand] regarding plaintiffs' termination for convenience claim."
Plaintiffs question this assessment.(4) General Dynamics observes that
"[d]uring the drafting of the May 1995 reports, Miller consulted with, and
received comments from the Department of Justice in order, in Miller's words,
'to make sure we were all singing from the same sheet of music in terms of the
final report.'"
Mr. Miller's analysis was
helpful but marginally useful in determining the proper level of incurred
costs. He acknowledged that the audit involved making determinations that were
"straight up and down accounting type of decisions. . . . We viewed our
role as providing . . . only an audit report that was advisory . . . in nature,
and that we wouldn't be making ultimate determinations that either the TCO or
the person sitting in the place of the TCO would have to make."
Defendant's counsel confirmed, "Miller has not been offered to provide
opinions under [FAR] 49.201. . . . Mr. Miller is here to testify and we're
offering him to testify regarding his conclusions as to allowability,
allocability and reasonableness under FAR part 31." Miller understood that
his role was to provide accounting advice and his opinion regarding FAR Part
31, but that the court's inquiry must include a consideration of FAR Part 49 as
well.
Tension Between FAR Part 31 and FAR
Part 49
Defendant argued that FAR
Part 31 should be the focal point of the court's analysis; plaintiffs
emphasized FAR Part 49. FAR 49.113 provides that "[t]he cost principles
and procedures in the applicable subpart of Part 31 shall, subject to the
general principles in 49.201, . . . be used." (emphasis added). See
also Codex Corp. v. United States, 226 Ct. Cl. 693, 698-99 (1981). Part 31
generally may be described as establishing a formulaic, accounting-based
structure, while Part 49 provides an equity-based framework. Because Part 31 is
subject to the general principles of 49.201, we do not apply strict cost
accounting principles here. "The use of business judgment, as
distinguished from strict accounting principles, is the heart of a settlement."
FAR 49.201(a). We cannot ignore equitable considerations and reasonable
business judgment in our deliberations.(5)
Still, plaintiffs bear the
burden of proving their termination for convenience damages. See Lisbon
Contractors, Inc. v. United States, 828 F.2d 759, 767 (Fed. Cir. 1987); FAR
31.201-3(a); see also Bath Iron Works Corp. v. United States, 34 Fed.
Cl. 218, 231 (1995), aff'd, 98 F.3d 1357 (Fed. Cir. 1996). The costs
considered in a termination for convenience recovery must also satisfy the
general requirements of FAR Part 31 -- that the costs be reasonable, allowable
and allocable. See FAR 49.113; see also FAR 31.201-2 to 31.201-4
(outlining the requirements of allowability, reasonableness, allocability,
respectively); 31.205-42 (providing cost principles "peculiar" to
termination situations)).
Overall Lack of Evidence that
Plaintiffs "Padded" their Costs
Defendant had little
evidence that plaintiffs attempted to inflate their costs. One would expect to
find some improper charges claimed through inadvertence or negligence, if
nothing else. But generally we were not provided with evidence of inflated
costs claims through bad faith, negligence, or otherwise.(6) Most of plaintiffs' costs were
incurred during a time when they had no reason to think that the costs would be
reimbursed.
This opinion will show that
for the most part, we found no basis for questioning the reasonableness,
allowability, or allocability of plaintiffs' claimed costs.
DISCUSSION
I.
SUBCONTRACTOR SETTLEMENTS
FAR 49.104 provides, in
pertinent part:
After receipt of the notice
of termination, the contractor shall comply with the notice and the termination
clause of the contract, except as otherwise directed by the TCO. The notice and
clause applicable to convenience terminations generally require that the
contractor --
. . . .
(g) Settle outstanding
liabilities and proposals arising out of termination of subcontracts, obtaining
any approvals or ratifications required by the TCO . . . .
"Contractors shall
settle with subcontractors in general conformity with the policies and
principles relating to settlement of prime contracts in this subpart and
subparts 49.2 or 49.3." FAR 49.108-3(a). "The use of business
judgment, as distinguished from strict accounting principles, is the heart of a
settlement." FAR 49.201(a). "The primary objective is to negotiate a settlement
by agreement." FAR 49.201(b). "In appropriate cases, costs may be
estimated, differences compromised, and doubtful questions settled by
agreement." FAR 49.201(c).
Prime contractors must
terminate all subcontracts related to the terminated portion of the prime
contract and settle all liabilities and proposals arising out of termination of
the subcontracts. FAR 49.104(b), (g). The A-12 contract entitles the
contractors to the cost of settling and paying subcontractor termination
proposals. FAR 52.249-2(f)(2)(ii). Such costs are "generally
allowable." FAR 31.205-42(h); FAR 31.205-42(g)(1)(i)(B).
FAR 49.201 requires that
the contractor be compensated fairly through the exercise of judgment. Cost and
accounting data may be employed but are not rigid measures for determining fair
compensation. Settlements may be executed on a "bottom line" basis. See
FAR 49.201(b) ("The parties may agree upon a total amount to be paid the
contractor without agreeing on or segregating the particular elements of costs
or profit comprising this amount").
Contractors are entitled to
the costs of subcontractor settlements provided the settlements are
"arrived at in good faith, . . . reasonable in amount, and . . . allocable
to the terminated portion of the contract." FAR 49.108-3(c). A settlement
will be approved when it is the product of "arms-length bargaining,
without collusion, and reflect[s] a sound exercise of prudent business
judgment" by the prime contractor. General Electric Co., ASBCA No.
24111, 82-1 BCA ¶ 15,725 at 77,806 (March 29, 1982), aff'd on recon.,
ASBCA No. 24111, 83-1 BCA ¶ 16,207, at 80,529 (December 1, 1982). The FAR does
not encourage second-guessing of the exercise of business judgment. Id.
at 77,804.
Subcontractor settlements
may comprise the subcontractor's incurred costs, profit or loss adjustment, and
the subcontractor's settlement expenses. If the sum is reasonable, allocable,
and allowable, the subcontractor is entitled to recovery.
We ruled that defendant
could not question plaintiffs' business judgment or negotiating tactics, but
that it could submit evidence of investment, bad-faith, self-dealing, or less
than arms-length transactions. Defendant also could show evidence of willful
neglect or wrongdoing attributable to the plaintiffs, if applicable.
A. Norden
Norden had a subcontract
with General Dynamics to provide a radar system for the A-12. General Dynamics
terminated Norden for default in April 1989, and Norden sued General Dynamics
in June 1989. The parties settled this litigation in 1992 for approximately $40
million. As part of its termination settlement proposal to the Government,
General Dynamics claimed the $40 million amount of settlement, $10 million in
legal fees incurred in its defense, and $10.7 million in reprocurement costs.
We ruled in August 1997
that General Dynamics' decision to settle with Norden was made on the basis of
sound business judgment. The Government argued that General Dynamics could not
recover costs associated with the Norden settlement because it terminated
Norden for default. Testimony at trial established that (1) General Dynamics
faced a potential liability of $160 million; (2) a trial would have been
litigated before a jury in Norden's home state of Connecticut; (3) security
problems would have made trial dangerous and perhaps restrictive; and (4)
Norden could have raised General Dynamics' own schedule slippage in its
defense. General Dynamics determined that it was prudent to settle with Norden,
and we declined to second-guess that reasoned decision. See generally Nolan
Brothers, Inc. v. United States, 437 F.2d 1371, 1392 (Ct. Cl. 1971)
(holding that costs incurred as a result of a decision to terminate a
subcontractor for default were recoverable so long as the decision was
"one that a prudent business man would take in the circumstances").
B. Westinghouse
Westinghouse subcontracted
with General Dynamics in 1988 to develop and supply the combined-function
forward-looking infrared radar system for the A-12 aircraft. As a result of the
Norden termination in 1989, the subcontract was superseded by a new subcontract
requiring Westinghouse to develop and supply the multi-function radar systems
also. Westinghouse began work on the new contract late in the development phase
of the project. See McDonnell Douglas Corp. v. United States, No.
91-1204 (Fed. Cl. Aug. 21, 1997). The Government terminated the prime contract
in January 1991, and General Dynamics terminated Westinghouse in April 1991.
Westinghouse submitted a termination settlement proposal and request for
equitable adjustment in May. The parties negotiated a $73 million settlement in
August 1991. The Government challenges $51,099,249 of that settlement.(7)
1. Expedited Settlement
The Government argues that
Westinghouse and General Dynamics colluded or engaged in less than arms-length
dealing because of circumstances surrounding their settlement. That is, General
Dynamics departed from its internal procedures and settled with Westinghouse on
an expedited basis before an audit and claims analysis was performed. Defendant
suspects that General Dynamics expedited settlement so that it could enlist
Westinghouse's support in this litigation.
The Westinghouse settlement
was allocable, allowable, and reasonable. That the settlement was achieved on
an expedited basis does not taint its integrity. Settlement was made contingent
upon a successful audit. General Dynamics settled with Westinghouse long before
the prime contract termination was converted into one for convenience, and it
faced severe litigation risk. General Dynamics had no incentive to settle with
Westinghouse on a less than reasonable basis. Westinghouse sought $110 million;
the parties settled for $73 million.
2. Combined Loss Ratio
Defendant challenges
$27,573,468 due to an alleged improper calculation of Westinghouse's loss
ratio. The loss ratio is impermissible, according to defendant, because unlike
those applied to other subcontractor settlements, the loss ratio applied to
Westinghouse combined FSED, Lot I, and Lot II. This had the effect of
increasing Westinghouse's recovery and the Government's ultimate liability by
$27,573,468. "The impact of combining the loss ratio is to dilute the
impact [of] the loss ratio on the FSED portion of the contract which
represented 82% of the actual costs at termination," defendant argues.
General Dynamics states
that it imposed a combined loss ratio here because the subcontract required it.
Westinghouse subcontracted with General Dynamics initially to supply the
combined-function forward-looking radar system only. After General Dynamics
terminated Norden, its initial subcontractor, however, it assigned Westinghouse
the additional responsibility of developing and supplying the multi-function
radar system. In return for accepting the multi-function radar duties late in
the development phase, Westinghouse demanded that any loss ratio imposed
combine FSED, Lot I, and Lot II. Motorola was the only other subcontractor to
extract such a concession. General Dynamics did not impose a combined loss
ratio on Motorola because Motorola was not in a loss position at the time of
termination.
Loss ratios were segregated
for purposes of progress payments for more than a year after General Dynamics
and Westinghouse renegotiated the subcontract, but Westinghouse insisted that
they be integrated. General Dynamics' legal department agreed, and sought and
obtained Government approval. The Government argues that it approved the
combined loss ratio for progress payments only, not for final settlement. We
are not aware that Government approval is required in such circumstances.
Moreover, there is no prohibition against combining loss ratios. The
application of a combined loss ratio to the Westinghouse subcontract does not
demonstrate collusion or less than arms-length dealing. General Dynamics
believed that it was required to combine FSED, Lot I, and Lot II for purposes
of assessing any loss ratios, and that position was not unreasonable. The
contract does not limit the application of a combined loss ratio to progress
payments only.
Moreover, Westinghouse
demanded that loss ratios be combined as consideration for agreeing to perform
the multi-function radar contract late in the program. The first subcontractor,
Norden, was terminated more than a year into contract performance in 1989.
Westinghouse's performance period was compressed. General Dynamics needed
exceptional performance from Westinghouse, and got it. It was reasonable for
General Dynamics to agree to a combined loss ratio.
3. Low Range Estimate at Completion
Value
General Dynamics engineers
generated a range of estimate at completion (EAC) values that settlement
negotiators could employ to compute the loss ratio for the Westinghouse
settlement. The values ranged from low to high and General Dynamics used a low
value at settlement. Specifically, General Dynamics' engineers recommended a
range of possible EACs from $163 million to $175 million. The negotiators
actually used an EAC of $165.8 million. The Government contends that they
should have used an EAC at the mid-point of the range. This would have
increased the loss adjustment and reduced the Government's liability by
$3,602,687. It was unreasonable for the contractor to select a lesser EAC value
within the estimated range, according to the Government.
General Dynamics derived
the estimate at completion from a reasonable exercise of business judgment and
consideration of other information in addition to engineering analysis. It
weighed competing considerations and input from financial and business
personnel. This exercise resulted in the departure from a mid-point in the
estimated range.
That General Dynamics'
negotiators employed a value from the low end of the range does not invalidate
it. The FAR expressly permits a contractor to employ business judgment in
reaching a settlement with the subcontractor. See FAR 49.201(a).
Engineering was only one source of information that General Dynamics considered
before selecting its EAC; it consulted business and financial personnel, and
weighed competing considerations. This is the essence of the exercise of
business judgment.
The Government's solution
-- arbitrarily to choose the mid-point of the engineering department's range --
is not consistent with the exercise of business judgment. We find no support
for the position that it is per se unreasonable for a contractor to
select a value that is below the mid-point of an estimated EAC range.
4. Profit on Lots I and II
General Dynamics applied a
loss ratio of 84.87% on Lot I progress payments prior to terminating
Westinghouse. Lot II progress payments were suspended in December 1990.
Defendant questions certain costs because General Dynamics settled with
Westinghouse allegedly on the basis of 15-20% profit margins. Defendant challenges
$9,397,228 because it appears that General Dynamics credited Westinghouse with
profit for Lots I and II while the contract was in a loss position. The
Government argues that it was improper to pay Westinghouse profit. General
Dynamics denies that it paid Westinghouse profit, but that instead it applied a
combined loss ratio of 85.73% to the Westinghouse contract.
If the loss ratio is
segregated, it may appear that Westinghouse received profit for Lots I and II.
We stated that it was reasonable for General Dynamics to combine loss ratios in
the circumstances of this case, however. The combined loss ratio precluded
Westinghouse from making profits. The Government's argument assumes that
General Dynamics was required to segregate loss ratios, but the contract did
not require segregation.
5. Inventory Transfer
Upon termination of its
sub-contract with General Dynamics, Westinghouse transferred inventory
originally slated for use on A-12 to non-A-12 programs on a total cost basis.
Westinghouse's termination settlement proposal, Form SF 1436, took into account
Transferred Costs as well as Disposals and Other Credits. Westinghouse placed
the transferred cost amount on line 16, which accounts for disposals and other
credits, then applied a loss ratio to that amount.
The Government argues that
the entire amount of transferred inventory should have been included in
Disposals and Other Credits without taking into account the loss ratio. This
would have further reduced the Government's liability.
DCAA Contract Audit Manual
§ 12-311 provides instruction as to the type of items included within the
Disposals and Other Credits line on Form SF 1436. The section states in part:
Credit amounts included in
a settlement proposal normally represent (1) an offer by the contractor to
purchase inventory at less than cost, (2) the proceeds from the sale of
termination inventory, or (3) a combination of (1) and (2) . . . .
Westinghouse transferred
common items at full cost to a non-A-12 program. It did not offer to purchase
or sell inventory. Thus, the cost of the transferred inventory should not be
included at all on line 16 (Disposals and Other Credits). The plain language of
DCAM § 12-311 suggests that the Government's interpretation is incorrect.
Westinghouse transferred common
items for other uses as instructed by FAR 31.205-42 and FAR 45.606-2. Although
Westinghouse included the transferred costs of the inventory under Disposals
and Other Credits on Line 16, it applied a loss ratio to the costs. This has
the same effect as if Westinghouse had included the costs on Line 7
(Transferred Costs), then applied the loss ratio to the remainder. While it
would have been proper to include the entire amount of transferred costs on the
transferred cost line, thereby reducing total costs before applying the loss
ratio, Westinghouse essentially removed those transferred costs from the
settlement equation by applying a loss ratio to them on the Disposals and Other
Credits line.
Moreover, according to
DCAA's training manual (Audit of Terminated Contracts, FAO Training Course
2211), removal of common items from program costs prior to applying a loss
ratio is required. While Westinghouse did place the transferred cost amount on
the Disposals and Other Credits line, it essentially took the cost of those
transferred items out of the settlement proposal by applying the loss ratio to
them. The Government's liability remains the same.
6. Consideration of REAs
Westinghouse submitted
requests for equitable adjustments totaling $44.5 million as part of its
termination settlement proposal. General Dynamics settled those claims for $11
million, but it did not determine who was responsible for the adjustment.
General Dynamics did not verify that REAs paid to Westinghouse arose solely
because of government fault, but paid the REAs and claimed $10 million as part
of its termination settlement proposal. Defendant contends that it cannot be
held liable for such claims when General Dynamics does not prove that
government conduct or inaction caused the adjustment. The Government challenges
$10,098,968(8) of the settlement as
"pending."
This argument is
essentially a reiteration of a government motion that we denied earlier. We
stated before trial that the court would "consider the reasonableness of
challenged subcontractor REA payments on the same basis as other costs
allegedly incurred." McDonnell Douglas Corp. v. United States, No.
91-1204, at 2 (Fed. Cl. June 13, 1997) (denying defendant's motion for
pre-trial determination that plaintiffs cannot recover amounts claimed for
their subcontractors' requests for equitable adjustment). Costs are reasonable
so long as they do not result from plaintiff's willful neglect or wrongdoing. Id.
at 1. Settlements must be negotiated in good faith and incorporate the exercise
of business judgment.
Westinghouse sought
equitable adjustments totaling $44.5 million. General Dynamics obtained advice
and assistance from technical, financial, and legal representatives before
settling these claims. Engineers for General Dynamics reviewed the requests for
equitable adjustments and determined that Westinghouse was entitled to an
adjustment ranging from $12 million to $18 million. General Dynamics' lawyers proposed
a range of adjustment from $9 million to $11 million. The actual $10 million
adjustment incorporated the exercise of business judgment. Defendant has not
shown that plaintiff's willful neglect or wrongdoing prompted the claims; nor
is there a hint of bad faith.
C. Other Subcontract Challenges
We do not reprise the legal
standards described in rulings above concerning Norden and Westinghouse. It is
sufficient to state that no credible evidence of bad faith, willful neglect, or
wrongdoing has been presented with respect to any of the following
subcontracts: General Electric Aircraft Engines, Allied-Signal-Torrance; Allied
Signal-Teterboro; SJ & LA-Hughes; Harris Corporation; SCI Technology, Inc.;
Litton Systems; Sundstrand Aerospace; Menasco Aerospace; and Parker Hannifin.
McDonnell Douglas' claimed incurred costs with respect to these subcontracts
may be awarded, as they are reasonable, allowable and allocable. Plaintiff
General Dynamics' claimed incurred costs with respect to Litton Amecon; GE - Utica;
Martin Marietta; Models and Tools; Teledyne Ryan; Hewlett Packard; Motorola;
Arkwin; Struthers Dunn; Parker Hannifin; and Hexcel also are reasonable,
allocable, and allowable.
II.
SUBCONTRACTOR REQUESTS FOR EQUITABLE
ADJUSTMENTS
The Government challenges
various subcontractors' requests for equitable adjustments, because "it is
now uncontroverted that neither General Dynamics [n]or McDonnell Douglas even
attempted to establish Government liability for the REAs." We stated in
June 1997 that the court would "consider the reasonableness of challenged
subcontractor REA payments on the same basis as other costs allegedly
incurred." Plaintiffs exercised sound business judgment with regard to
paying REAs to subcontractors. A court should not second-guess contractors who
make reasoned decisions in such circumstances, as noted above. Such costs
claimed by plaintiffs are reasonable, allocable, and allowable.
We have even less reason to
question plaintiffs' costs with respect to requests for equitable adjustments
in this area than in the Westinghouse situation, given the evidence presented.
The Government argues that "there is a requirement that a prime contractor
evaluate a subcontractor claim to determine Government liability." If so,
this is not a case in which the plaintiffs blindly passed on a claim for costs
by the subcontractor to the Government. We see no compelling reason for
subcontractors' requests for equitable adjustments to be treated differently
from other subcontractor settlement costs. See FAR 49.201(b) ("The
parties may agree upon a total amount to be paid the contractor without
agreeing on or segregating the particular elements of costs or profit
comprising this amount"). As Allen Broesche, a witness for General
Dynamics, testified: "It was our money, and we reached a reasonable
settlement." Plaintiffs had no expectation that any of these expenses
would be reimbursed by the Government while negotiating with subcontractors
over REAs or any other settlement expenses. We cannot disallow these costs.
III.
DIRECT MATERIAL
[T]he audit team performed
audit procedures, including sampling, to evaluate the allowability,
allocability, and reasonableness of the [General Dynamics] and [McDonnell
Douglas] direct material line (Line 1) items in their January 1994 Update.
These procedures were supplemented by Coopers' review of the February 1997
Update, and, as a result, Coopers questioned a total of $14,955,000 in MDC
direct material costs . . . and $53,143,152 of GD's proposed direct material
costs. Additionally, Coopers categorized $9,935,196 as pending for MDC due to
MDC's failure to perform a commonality study. In general, the questioned direct
material costs include overpayments to vendors, defective items that were
returned and not properly credited, items actually used or usable for other
programs, excess purchases, purchases incurred long before required, and
inadequate or sloppy documentation.
A. General Dynamics - Direct
Material
1. Sample Testing of General
Dynamics' Costs
Coopers & Lybrand's
audit team "reviewed documentation to verify necessity, cost, payment,
receipt, physical existence, and disposition." Mr. Miller testified that
General Dynamics did not provide the audit team with appropriate termination
inventory schedules. Robert Wright(9) generally agreed that General
Dynamics' inventory schedules were not available. According to Defendant,
General Dynamics' 'accounting system' was incapable of providing the audit team
with termination inventory schedules, as required by the FAR, which would have
identified the current physical location and estimated costs of material that
GD purchased from vendors." As a result, the audit team used an accounts
payable system and statistically selected transactions for further
testing."
Using audit sampling
procedures, the audit team selected for review 47 items by vendor and purchase
order number. Mr. Miller testified that in developing the sample to be tested,
the audit team received technical assistance from the DCAA office in Memphis,
Tennessee. After testing the "sampled items," the audit team met with
General Dynamics personnel to seek additional explanation or further
documentation as appropriate. After evaluating the responses the audit team
either would withdraw the preliminary exceptions or leave them in place,
depending on the documentation available.
"Dollar unit
sampling" focuses on the dollars in a given accounting population. The
audit team used this method for review of General Dynamics' incurred direct
costs. According to the DCAA Contract Audit Manual, dollar unit sampling is a
valid technique to account for the reasonableness of costs incurred for direct
material. See DCAM B-503.1. We agree with the Government that audit
sampling is recognized by the accounting and auditing profession as being a
proper and appropriate method for review.
Miller testified that in
dollar unit sampling "you're not looking at every dollar in the
population, you're only looking at certain dollars in the population, but those
are representative and will be representative of the rest of the
population." When errors in the sample population are found, an error
proportion is calculated and used to determine the extrapolation percentage.
"Of approximately 22 million [dollars] reviewed, Coopers identified $6.36
million of questioned costs within the sample. Using dollar unit sampling
procedures, Coopers projects the total amount of questioned direct material
costs to be approximately $53,143,152."
While we recognize that the
audit team's methods applied proper sampling techniques, we do not agree with
all of their findings and extrapolations. Mr. Miller questioned many direct
costs incurred on the grounds of allocability and allowability. Where
sufficient evidence of allowability, allocability and reasonableness of costs
are found, however, the court must sustain those costs as incurred.
2. Lack of Documentation
a. Bell Helicopter
General Dynamics purchased
a tool for the wingfold of the A-12 from Bell Helicopter. Defendant claims that
General Dynamics paid Bell Helicopter "over and above the price listed in
the purchase order reviewed." The audit team questioned $2,671 of $23,055
paid to Bell Helicopter because it was not satisfied that General Dynamics'
documentation supported the costs claimed. General Dynamics explained that it
"could not locate the change order that would have explained the precise
reason for the second of two increases in the purchase price of the tool, which
increased the price from $20,384 to $23,055." The audit team extrapolated
a challenge of $885,135 in costs from the $2,671 figure.
Other documentation
supports General Dynamics' position. It paid Bell Helicopter $23,055 pursuant
to an invoice for the manufacture of an A-12 tool. Before issuing a check to
Bell Helicopter, General Dynamics' accounts payable clerk made a notation on
the check indicating that she had verified the invoice amount against the final
purchase order amount that had been entered by the buyer in the procurement
file. Mr. Miller acknowledged the existence of documentation indicating that
the change was for "rework." General Dynamics contends that it is
common for rework to be done during the manufacture of tools developed for a
RDT&E; here there is no dispute that Bell Helicopter was providing tooling
work.
The court's role is to
determine whether General Dynamics incurred the cost, whether it did so for the
A-12 contract, and whether it did so for a legitimate purpose. Although Mr.
Miller did not find these factors sufficient to document the increased cost,
evidence presented at trial satisfied the court that the entire cost was
allowable, allocable and reasonable. See, e.g., FAR 49.201(c).
b. Cohn and Gregory
The audit team challenges
the entire $7,714 the General Dynamics paid to Cohn & Gregory for PVC
piping and valves. After extrapolation, this becomes a challenge of $7,640,132.
The audit team sought a
"requirements listing" to determine whether the items purchased from
Cohn & Gregory were required for the A-12. General Dynamics provided no
such list, but submitted the declaration of an employee, Steve Wells. Mr.
Miller testified that this representation was not sufficient to make a
determination of allowability, allocability, or reasonableness. General
Dynamics acknowledged that it could not produce much documentation other than
the declaration. However, Mr. Wright testified that the PVC pipes and valves
were purchased for an environmental control test stand for the A-12. Mr. Wells
was the buyer of the material. His declaration stated that "[t]he fittings
and other hardware was purchased to build the test setup shown in the
drawings." An invoice from Cohn & Gregory, signed by Wells, contains a
unique A-12 work order number. This cost is properly awardable.
c. Fiber-Resin Corporation
General Dynamics claims
costs for tooling foam boards that were shipped to Cadillac Motor Car Division
as furnished material to be used to manufacture a tool for A-12 (Tool #
R15649). Coopers questioned $30,774 associated with this item for lack of
documentation "and an inability on the part of GD to demonstrate the use,
location, or disposition of this material." Cadillac was not a General
Dynamics A-12 vendor, but it was a vendor to Models & Tools, an A-12
subcontractor. Using its sampling technique, Coopers & Lybrand extrapolated
a challenge of $7,640,132 from the $30,774 questioned item.
Mr. Miller testified that
General Dynamics did not provide sufficient documentation to support this cost
item. Coopers & Lybrand reviewed an internal General Dynamics audit of
Models & Tools and found that General Dynamics' own analysis concluded that
Models & Tools' cost accounting system was inadequate. The cost accounting
system failed to identify the tooling foam boards, for example.
Payment was made to
Fiber-Resin, the producer of the foam board, while the board was shipped to
Cadillac. The type of foam board ordered is consumed during the production of a
tool. After termination, General Dynamics issued an abandonment certificate to
Models & Tools for Tool #R15649. This indicates that the tool, which was
classified as work-in-process, had no value. DCAM 2-202(a) provides that
because "audits frequently require a wide variety of skills, an auditor
may need technical assistance from other disciplines such as legal,
engineering, and production/quality control. The auditor should make
arrangements to secure any needed technical assistance from the ACO/plant
representative or responsible acquisition agency." General Dynamics argues
that Miller should have sought technical assistance in such a circumstance.
Plaintiff's documentary
evidence and its testimony concerning consumption of the foam board material
justify award of its costs.
3. "Expediting Charges"
Coopers questioned certain
of General Dynamics' direct material costs because General Dynamics paid
premium prices for expediting delivery of items "long before they were
actually required by GD." The Government points out that many of the
materials in issue still were on hand when the contract was terminated.
a. Stanley Aviation
The audit team challenged
$70,077 in expediting charges paid to Stanley Aviation for providing parts for
the A-12 full-scale mock-up. Miller questioned this amount at trial "due
to the fact that the item was not used at termination, yet it had been
expedited earlier." The sampling technique here creates a $6,626,207
challenge.
The minutes of a meeting of
the General Dynamics "Procurement Ad Hoc Committee" on September 21,
1989 include the following entry concerning the Stanley Aviation order: "Schedule:
The A-12 program schedule dictates the requirement for procurement to initiate
an expediting fee to authorize the supplier to perform to an expedited schedule
that supports the A-12 program needs." According to General Dynamics,
"the parts still were on hand at termination because the A-12 delivery
schedule was extended by 18 months in 1990, after these parts were
ordered." The full-scale mock-up was affected by this schedule change.
The Government did not
establish that when the purchase order was placed with Stanley Aviation,
General Dynamics should have known it did not need to expedite delivery.
General Dynamics points out that this is another area in which Miller could
have benefited from technical and contract assistance. See DCAM
2-202(a).(10)
General Dynamics made a
reasonable business judgment at the time the purchase order was made. The
fixed-price nature of the contract and the attendant cost risks undertaken by
General Dynamics, along with credible testimony at trial that General Dynamics
did not make the decision to incur expediting charges lightly, support this
conclusion. See, e.g., Boeing Aerospace Operations, Inc., ASBCA
Nos. 46274, 46275, 94-2 BCA ¶ 26,802, at 133,282 (March 21, 1994)
(reasonableness is judged by considering "all of the relevant
circumstances existing at the time of the incurrence of the costs")
(citing FAR 31.201-3), aff'd on recons., ASBCA Nos. 46274, 46275, 94-3
BCA ¶ 27,281 at 135,908 (November 9,1994).
b. Standard Pressed Steel & Kamatics
Coopers & Lybrand
challenges $3,007 in expediting charges to Standard Pressed Steel--extrapolated
to arrive at a $2,792,498 challenge. The entire amount of a $2,059 acquisition
of ball bearings from Kamatics is questioned as well. This amount is increased
to a challenge of $7,640,132. Mr. Wright testified that in both of these
situations, "expediting was done to meet a schedule of a subassembly, an
indentured-type system for manufacturing." As mentioned above, General
Dynamics had to consider carefully any decision to incur expediting charges.
The charges incurred here are properly awardable.
4. Other Direct Material Challenges
a. Sierra Alloys
Coopers & Lybrand
challenges $220,924 of a $421,764 purchase of 42 pieces of titanium from Sierra
Alloys, to be used for the inner wing engine bay doors and the inner wing. The
audit team could account for only 20 of the 42 pieces at termination, and it
challenged the cost of the other 22 pieces. The $220,924 challenge is
extrapolated to $4,001,974.
According to General
Dynamics, even if 22 of the pieces somehow were "lost," its
termination claim should be reduced only by the fair market (salvage) value of
those 22 pieces. See FAR 49.204 and DCAM 12-304.10 (with respect to
termination inventory that is undeliverable to the government because it was
damaged, destroyed, or lost, the fair value of such undeliverable material
should be deducted from the termination settlement proposal). General Dynamics
points out that proceeds from the sale of 12 pieces of scrap garnered $17,765
-- approximately $1,480 each. Applying this average price to the 22
"lost" pieces, the value of the challenged pieces totals $32,560.
We find that a $32,560
deduction is appropriate because that is the fair value of the lost material.
Extrapolating from that figure, we deduct $589,815 from plaintiffs' claim.
b. Stewart-Warner
This challenge is to
$36,315 of a $435,780 purchase of 12 instrument landing systems from
Stewart-Warner. The audit team could account for only 11 of the 12 items at
termination, so it challenged the entire acquisition cost of the twelfth item.
Using its sampling methodology, the audit team extrapolates a challenge of
$636,678.
General Dynamics argued
that because records were available for the other eleven items, it should be
entitled to a credit because "all parts have been accounted for." The
Government contends, that "[t]he fact that GD was able to provide adequate
documentation regarding the eleven that went to salvage suggests that the
twelfth was not salvaged."
General Dynamics ordered,
received, and paid for 12 items for use on the A-12 contract. It rejected one
of the 12 items and returned it to the vendor. The vendor later shipped the
twelfth item directly to the A-12 manufacturing facility in Tulsa, Oklahoma.
General Dynamics attempted to return the items to Stewart-Warner after the
contract was terminated, but Stewart-Warner refused to accept them. General
Dynamics salvaged eleven of the items for little value. We have no
documentation concerning disposition of the twelfth item, but these facts are
not in dispute.
General Dynamics argues
that "it is reasonable to rely on the termination procedures established
by the contractors, which reasonably attempted to account for and dispose of
all A-12 inventory." It notes further that the contract had been
terminated for default, so "at the time GD disposed of the A-12 inventory
it had no guarantee it ever would recover its incurred costs, and the company
thus had an obvious incentive to dispose of its inventory in a manner that
would recover as much of the cost of the item as possible."
We cannot find sufficient
grounds for awarding the value of the twelfth item as an incurred cost. As
mentioned above in the Stewart-Warner context, the FAR and DCAM contemplate
that when inventory is lost, the fair value of that material should be deducted
from the termination settlement proposal. That could be accomplished here by
considering the value of the eleven items sold for salvage to arrive at a value
for each item, and then applying that value to the twelfth item. We did not
hear evidence of the salvage value of those items, other than testimony that
they had very little value. We therefore cannot impute a salvage value to the
twelfth part, and instead must deduct the acquisition cost of the twelfth item
from General Dynamics' proposal. This method is consistent with the
Government's challenge. We therefore sustain the extrapolated challenge argued
by the Government, $636,678.
c. Universal Alloy
"Coopers
questions certain costs for materials in excess of the requirements of the A-12
FSED contract and Lots I and II options. For example, GD purchased aluminum from
Universal Alloy for use on various programs, including the A-12. GD originally
charged the costs of a small portion, only 24 feet, to the A-12 contract; in
fact, the purchasing document specifically stated that the remainder of the
aluminum was for "various prime contracts." However, more than two
years after termination, GD charged an additional 262 feet of the aluminum to
A-12. As there is no evidence that the A-12 program required aluminum in excess
of 24 feet, Coopers questions all costs for aluminum in excess of that amount.
The challenge based upon
these costs is $7,640,132--extrapolated from an initial figure of $1,670.
We are persuaded that
allocation to the A-12 contract was reasonable. FAR 31.205-42(a) defines common
items as those "reasonably usable on the contractor's other work."
Testimony from Mr. Wright indicates that although some aluminum may have been
available for use on other programs if needed, no such need developed. The
aluminum had been acquired originally for the A-12 program. Because the
aluminum did not prove to be useful on another program, General Dynamics
transferred an additional 262 feet of aluminum (at a cost of $1,670) into the
A-12 program on February 13, 1993. At the time of the transfer, the contract
was considered to be in default. Thus General Dynamics had no incentive to
transfer the costs to A-12 when reimbursement by the Government was unlikely.
We find that this cost is properly awardable to General Dynamics.
d. Voi-Shan Manufacturing
Defendant challenges a $1,902
purchase of 46 bolts from Voi-Shan Manufacturing--extrapolated to arrive at a
challenge of $7,640,132. Defendant's position is that these items should have
been returned to the manufacturer, likely for full credit.
Plaintiff points out that
FAR 45.605-2 permits a contractor to recover from the Government a restocking
charge of up to 25% of the cost of the returned items, as well as
transportation and handling costs associated with the return. See also
DCAM 12-304.8 ("The contractor may not include the cost of returned
property in the settlement proposal but may include the transportation,
handling, and restocking charges for the returned property"). Mr. Miller
conceded that the cost of returning the bolts may have met or exceeded the
entire $1,900 purchase price.
General Dynamics judgment
not to return the bolts was sound, given the doubtful economic value of
returning them.
B. McDonnell Douglas - Direct Material
The Government divides
McDonnell Douglas' direct material costs into three categories: (1) contractor
furnished equipment; (2) subcontract costs; and (3) manufacturing material. In
reviewing McDonnell Douglas' claimed direct material costs, the audit team
tested the "control, physical existence, and disposition or termination
inventory on hand at the time of the audit."
Unlike General Dynamics'
accounting system, McDonnell Douglas' records permitted the audit team to
review incurred direct costs through non-statistical sampling means:
MDC's records permitted the
Audit Team to conduct physical inventory verification testing with regard to
termination inventory on hand in August 1994. Mr. Miller testified that, as a
result of these procedures, the Audit Team found discrepancies in quantity,
description, or location in nearly one-third of the 76 items that the Audit
Team selected for verification. Coopers could not project the results of this
sample to the entire population because MDC did not provide priced inventory
schedules. Therefore, Coopers questions only $75,042, which represents the specific
items quantified.
Physical inventory
verification testing is a proper sampling method. If sufficient evidence
sustains a claimed cost, however, the cost should be awarded.
1. Damaged and Defective Inventory
The Government asserts that
after the physical inventory procedures, McDonnell Douglas supplied
documentation as to the location of several missing "CFE/major
subcontracts items selected for physical inventory." McDonnell Douglas had
also returned certain of these items to its vendors or labeled them as
defective, damaged or rework items. According to the Government,
"[McDonnell Douglas] provided no satisfactory evidence that it took credit
for these damaged or defective components as a part of the subcontractor
settlement process and, accordingly Coopers questions $1,439,405 in associated
costs."
Mr. Hancock testified that
the costs to repair such items were added to increase subcontractors' estimates
at completion. This would have the effect of reducing the subcontractors'
recovery. On the record before the court, we cannot say that these costs are
unreasonable.
2. Common Inventory
The Government also
contends that during physical inventory testing, the Defense Plant
Representative Officer's technical representatives identified material that
could be used on other programs. "The costs of items reasonably usable on
the contractor's other work shall not be allowable unless the contractor
submits evidence that the items could not be retained at cost without
sustaining a loss." FAR 31.205-42(a). Additionally, "[a]ny acceptance
of common items as allocable to the terminated portion of the contract should
be limited to the extent that the quantities of such items on hand, in transit,
and on order are in excess of the reasonable quantitative requirements of other
work." Id. Additional procedures were performed by the Coopers
& Lybrand audit team "to identify amounts of termination stores
material that MDC actually used in other programs and, in some cases, purchased
from vendors after termination." Based on these procedures, the Government
questions a total of $764,282 as "common inventory" because the costs
claimed may not be included in termination costs if the inventory could be used
on other programs, as alleged here.
Mr. Miller acknowledged
that the contracting officer should make a determination whether inventory is
common, but that the Government did not do so in this case. He further
acknowledged that the Government did not provide an inventory verification
report, did not appoint a plant-wide clearance officer, and did not make an
assessment of commonality at the time of termination. He stated that with
respect to post-termination inventory, the Government's position was that
"they wouldn't do anything in terms of dealing with the contractors on
inventory, other than to let them know that there had been a termination for
default."(11) He stated that "in general,
my understanding is that they didn't get involved or want to be involved in
that particular process because it was a termination for default." Mr.
Hancock testified that all of the direct material costs in the company's claim
were in excess of its needs. He detailed McDonnell Douglas' procedure for transferring
common items. We cannot question McDonnell Douglas' claims in this area.
3. Panstock Cost Transfer
The audit team conducted a
review of pre- and post-termination journal vouchers, and discovered a February
22, 1991 entry allocating $2,611,179 of panstock to the A-12 program. The
Miller report questions the $2,611,179 as a common item unallowable under FAR
31.205-42.
As McDonnell Douglas uses
the term, panstock describes low-value, high volume material. Michael Cromer(12) testified that panstock can be
either common and used for multiple programs, or unique and used on a single
program.
Hancock and Cromer
testified that McDonnell Douglas systematically moved panstock and other
inventory to other programs where it could, and that its incurred costs do not
include any "common items," for which the Government is entitled to
credit under FAR 31.205-42(a). In short, McDonnell Douglas sought to mitigate
its costs related to panstock.
Panstock should not be
treated differently from any other cost challenged as a common item. McDonnell
Douglas tried to limit the amount of panstock attributable to the A-12 contract
by attempting to find a use for it on other contracts. The remaining A-12
panstock exceeds McDonnell Douglas' needs; it remains a cost to which McDonnell
Douglas is entitled.
4. Fixtures Loaned to Other Programs
The Government maintains
that Coopers identified six significant test fixtures of physical inventory
that reportedly were being used on other McDonnell Douglas programs. The costs
for these items, however, remained in McDonnell Douglas' January 1994
termination settlement proposal update. According to the Government,
"McDonnell Douglas would not quantify the costs of the fixtures prior to
Coopers' issuance of its May 8, 1995 incurred cost audit report." After
the incurred costs audit report was issued, the Government learned through
discovery that McDonnell Douglas had "quantified the costs of five of the
test fixtures at $10,065,599." Coopers questioned this entire
amount.
Special test equipment is
an allowable and recoverable A-12 contract cost under FAR 31.205-40. Mr. Miller
admitted that the six test fixtures were built specifically for the A-12
contract. Miller argued that the costs nevertheless should be recovered under
other contracts because the test equipment had been loaned occasionally after
termination. In McDonnell Douglas' view, this simply mitigated costs to the
Government. McDonnell Douglas points out that "no contracting officer on
any other program has agreed to accept or pay any portion of the costs of the
special test equipment." It concludes based on the foregoing that there is
no basis to disallow this $10,066,000 in special test equipment costs under FAR
31.205-40. To do so would mean that it "could not recover its incurred
costs under the A-12 or any other contract."
We agree. These costs are
awardable to McDonnell Douglas.
D. Other Costs -- General Dynamics and McDonnell Douglas
1. Unabsorbed Overhead
The Government argues that
McDonnell Douglas cannot recover unabsorbed overhead costs:
Coopers identified and
questioned $12,538,718 in costs transferred, after termination of the prime
contract, from overhead pools to the Termination Proposal. These costs were for
facilities and were charged to overhead pools during the performance of the
A-12 contract. However, after termination MDC attempted to charge these costs
specifically to the A-12 contract, even though prior to January 8, 1991, other
contracts absorbed these costs pursuant to MDC's overhead allocation policies.
Neither Mr. Hancock nor Mr. Cromer, the two witnesses proffered by MDC to
testify to this issue could explain why the accounting basis of the treatment
of these overhead costs was different after termination than before.
Significantly, MDC presented no expert evidence to rebut Mr. Miller's testimony
that the costs in question were "by their very nature, overhead
costs." Indeed, MDC questioned these same types of costs in settling with
its subcontractor, SJ & LA-Hughes.
These alleged costs were,
in actuality, claims for unabsorbed overhead, inasmuch as they represented
overhead costs that MDC allegedly could not be [sic] recover, using the post
A-12 business base for allocating its overhead costs. As such, the law
proscribes their recovery in a termination for convenience. See DCAAM ¶
12-305.7(b)-(c); F. Alston, M. Worthington, & L. Goldsman, Contracting with
the Federal Government 360-61 (3d ed. 1992).(13)
McDonnell Douglas disputes
the Government's characterization of this expense as unrecoverable unabsorbed
overhead. Mr. Cromer testified that the $12,539,000 amount was specific to the
A-12 contract and that it represented the cost of idled A-12 facilities
accounted for exactly as DCAA has required on two other terminated
contracts.
The issue is whether it was
proper for McDonnell Douglas to remove such costs from the company's overhead
pools, and include them in the termination proposal as incurred for the A-12
program.(14)
Cromer and Hancock
testified that the idle facility costs were specific to the A-12 contract, but
were charged to overhead pools until termination. According to Cromer, the
practice of assigning depreciation into an overhead pool -- without regard to
whether it was a program-specific asset or a general administrative cost -- was
standard for McDonnell Douglas. In other words, the fact that an asset was in
an overhead pool did not necessarily identify that asset as a general,
administrative type of asset. Mr. Hancock testified that McDonnell Douglas
attempted to find alternative uses for the facilities that were specific to
A-12. He stated that after the facilities remained idle for some time, however,
"we decided that we would claim these costs."
Mr. Cromer testified that
claiming these costs in the A-12 termination proposal was not an aberration. He
described two prior incidences of adjusting overhead depreciation pools
following a convenience termination. Cromer testified that after the Tacit
Rainbow Program was terminated for convenience, the DCAA "specified in
their audit report that it should be charged directly to the termination
claim." Similarly, with respect to the Atlas program, costs in the
overhead pool were "moved from the overhead pool and charged directly to
the termination claim on the Atlas program."
These assets were
program-specific; their costs were incurred in performing the A-12 contract.
Asset costs assigned to overhead pools nevertheless can be program-specific,
and included in a cost proposal associated with the termination of that
program. Based on its prior experience with the DCAA, McDonnell Douglas sought
to recover incurred costs inextricably associated with the A-12 program. We
find that these costs are reasonable, allowable, and allocable.
2. Material Handling Expense
Coopers and Lybrand
questioned $6,700,000 in material handling expense charges at General Dynamics
related to unliquidated progress payments. Material handling charges are
incurred when material is handled as it arrives. According to defendant,
General Dynamics is "attempting to charge the Government for costs that
were not and could not possibly have been incurred."
The base used to calculate
its material handling expenses includes the amount of unliquidated progress
payments paid by General Dynamics to its subcontractors. Mr. Miller testified
that he challenged these costs because "they were payments included in the
termination for convenience proposal for material handling expenses, overhead
expenses for material handling, that were applied to progress payments that
didn't represent deliveries and shipments."
General Dynamics notes that
the costs related to material handling are principally labor, such as "the
costs of paying people to move items in and out of warehouses and to help
procure material."(15)
We find that the material
handling costs noted by General Dynamics were incurred. It had used the same
accounting system before with Government approval. The system provided a method
whereby General Dynamics could allocate material handling costs to different
contracts, thus accounting for A-12 expenditures properly. General Dynamic's
accounting system was not unreasonable. We see no reason to impose a new
allocation method upon plaintiff retroactively. See Litton Systems, Inc.
v. United States, 449 F.2d 392, 399 (Ct. Cl. 1971).
3. Excessive Overtime
a. General Dynamics
Coopers listed as pending
$3,829,421 of General Dynamics' overtime expenses because the company
apparently could not explain adequately why it experienced overtime hours in
excess of that estimated in its Best and Final Offer.
No legal authority mandates
that overtime cannot exceed the target estimates made in a BAFO. This was an
incentive contract. Plaintiffs point out that Mr. Miller lacked the technical
expertise to appreciate the need for significant overtime in General Dynamics'
performance of the contract. See DCAM 2-202(a).
The standard that we employ
to determine the awardability of the overtime expenses claimed here is whether
they are allowable, allocable, and reasonable. See, e.g., Worsham Constr.Co,
ASBCA No. 25907, 85-2 BCA ¶ 18,016, at 90,369 (March 22, 1985). Testimony at
trial established that the overtime was incurred in performance of the A-12
contract. The overtime did not exceed an amount that would have been incurred
by a prudent business person, and therefore is allowable. See, e.g., FAR
31.201-2, -3, -4.
b. McDonnell Douglas
The contract did not limit
overtime. Additionally, it was not necessary for the contracting officer to
approve overtime before McDonnell Douglas could incur the expense. We find that
$11,605,000 challenged by the Government here is properly awardable to
McDonnell Douglas.
4. General Dynamics Offload
General Dynamics
transferred a number of tasks to McDonnell Douglas for completion during the
course of performance. The audit team grew concerned about costs related to
such tasks. "Because the potential duplication of effort has not been
quantified by either MDC or GD, Coopers determined that costs associated with
this effort may represent costs that GD experienced as overruns."
According to defendant, this establishes that plaintiffs did not meet their
burden of proving entitlement to these costs: "Neither plaintiff presented
evidence as to whether the work in question was a duplication of effort which
might be unreasonable for the plaintiffs to recover from the Government."
Mr. Hancock's explanation
of the transfer of certain tasks was simple: "McDonnell Douglas could
build them quicker than General Dynamics could." He testified that he knew
of no duplication of function, even though "[t]owards the latter part of
1990, the issue was discussed at almost every meeting."
We have no basis to suspect
duplication of efforts between plaintiffs other than, as Miller termed it
during trial, "healthy auditor skepticism." We found no evidence of
duplication. This cost is properly awardable.
5. Relocation Expenses
a. General Dynamics
The Government challenges
relocation costs of $2,931,977 incurred by General Dynamics. Defendant states
that the "benefitting" contract should be charged for the relocation
expenses and not the A-12 contract. That is, "if an employee is
transferred to another program, for example, the F-16 or the F-18, then those
programs and not the A-12 should pay for those costs." Defendant invokes
FAR 31.205-35(e), which provides that "costs of family movements and of
personnel movements of a special or mass nature are allowable. The costs,
however, should be on the basis of work (contracts) or time period
benefited."
General Dynamics argues
that these relocation expenses benefitted the A-12 contract within the meaning
of FAR 31.205-35(e). Further, the costs are properly allocable to the A-12
contract as continuing costs after termination, pursuant to FAR 31.205-42(b).
To perform the contract, General Dynamics relocated employees from Ft. Worth to
assignments in other locations, such as St. Louis, Tulsa, Patuxent River, and
Alamogordo. These employees returned to Ft. Worth after termination. General
Dynamics included the costs of returning such employees to Ft. Worth in its
Best and Final Offer, which makes these expenses an "explicit premise of
the contract."
FAR 31.205-42(b) provides
that "costs which cannot be discontinued immediately after the effective
date of termination are generally allowable." The DCAM provides, in
illustrating this FAR provision:
For example, the contractor
may have contract personnel at a remote or foreign location or there may be
personnel in transit to or from these sites. The cost of their salaries or
wages would be allocable to the terminated contract for a reasonable period
required to transfer the personnel to sites for termination or used on the
contractor's other work.
DCAM 12-305.7(a)(1).
"No principled distinction
can be drawn between the cost to relocate an employee after termination and the
cost of that employee's salary while he relocates," according to General
Dynamics. We agree, especially because the BAFO included a reference to
relocation. The costs incurred to return the contractors' employees to their
home base after termination are allocable to the A-12 contract. They are
properly included in plaintiffs' termination for convenience recovery.
b. McDonnell Douglas
The Government challenges
$78,000 in relocation costs claimed by McDonnell Douglas. Relocation costs were
included in the contractors' proposals. As stated above, FAR 31.205-42(b)
recognizes that "costs which cannot be discontinued immediately after the
effective date of termination are generally allowable." The DCAM provision
illustrating FAR 31.205-42(b) provides examples of allowable termination costs,
but they are not meant to be exhaustive. When a contract is terminated, the
DCAM contemplates that the salary or wages of a worker may be charged to the
terminated contract for a reasonable period, while he is transferred to perform
other work or for termination activities. The cost of relocating McDonnell
Douglas' employees is similar to the example provided by the DCAM. McDonnell
Douglas' relocation costs are properly awarded.
6. Application of Overhead Rates to
Unallowable Costs
The Government notes that
"to the extent that unallowable cost is identified, a corresponding
adjustment to the amount of overhead costs needs to be made. In essence, if the
direct costs are reduced then overhead costs must also be reduced by the
approved rate to reflect the proper amount of overhead cost." We agree.
The adjustment stemming from our sustaining the Sierra Alloys challenge is
$80,144. The deduction in overhead costs resulting from the Government's
Stewart-Warner challenge is $86,511. Thus, an additional $166,655 will be
deducted from plaintiffs' incurred cost total.
7. Miscellaneous Costs
a. McDonnell Douglas Helicopter
Corporation Purchases
During audit field work at
the McDonnell Douglas Helicopter Corporation (MDHC), Coopers identified
$785,370 in inventory which was common to other programs and which MDC was
attempting to charge to the A-12 in violation of FAR 31.205-42. MDHC was unable
to provide documentation to support the incurrence of $166,000 of direct
material costs. There was also $84,865 in costs based on the use of billing
rates rather than proposed rates. Finally, Coopers questioned $41,441 for
incorrectly applied material handling charges. The total amount of costs
challenged relating to MDHC is $1,077,976.
We are generally satisfied
with the measures taken by plaintiffs in dealing with common inventory. An
earlier discussion describes the testimony that we heard from Mr. Miller and
Mr. Hancock relating to common inventory. While the common inventory portion of
this challenge is not a concern, we are not satisfied that McDonnell Douglas
has proven its entitlement to the other costs challenged by the Government. The
Government's challenge is sustained in the amount of $292,306.
b. Douglas Aircraft Company
Purchases and Common Bomb Racks
Coopers identified and
questioned $1,087,141 in direct material cost for which Douglas Aircraft
Company could not provide proper accounting documentation to support the
purchase. The costs incurred were for bomb racks that were built initially for
the A-12 at Douglas Aircraft Company. Prior to termination, the task of
building the racks was transferred to McDonnell Douglas Helicopter Corporation.
Separately, Coopers challenged $224,516 in costs incurred by Douglas Aircraft
Company related to common bomb rack materials. Mr. Miller testified that the
audit team was not provided with adequate documentation as to the propriety of
these costs.
Mr. Cromer offered
testimony supporting these costs. While documentation of the costs may not have
been ideal, the costs were documented nevertheless. Two sets of data were
provided; they more or less supported each other. The first was McDonnell
Douglas' cost analysis reports reflecting amounts billed by Douglas Aircraft
Company. The second consisted of Douglas Aircraft's cost incurrence records,
including requisition forms and "purchase order activity forms."
These costs may not be
documented sufficiently to satisfy the rigorous accounting standards employed
by Mr. Miller. We find, however, that these costs are reasonable, allowable,
and allocable.
c. Loss on Sale of Office Furniture
Mr. Miller questioned the
cost of office furniture as common items because such costs are expressly
disallowed by FAR 31.205-42. In its termination for convenience proposal,
McDonnell Douglas claimed a $1,262,000 loss on the sale of Tulsa facility
furniture. Mr. Hancock testified that except for a limited amount of furniture
that was transferred for the Government's credit, the furniture was in excess
of McDonnell Douglas' needs, and could not be used elsewhere after termination
despite efforts by McDonnell Douglas to find an alternative use.
Testimony at trial
established that the furniture was purchased for the A-12 contract, and that it
was sold at auction after termination. McDonnell Douglas claims the resulting
loss. The costs appear to have been reasonable, allocable, and allowable. See
generally FAR 31.205-16(a) (gains and losses from the sale, retirement, or
other disposition of depreciable property shall be included in the year in
which they occur).
d. Termination Training
Coopers & Lybrand
challenges $198,000 for termination training provided by Petersen & Co.
because it was not specific to the A-12 program. Mr. Hancock's testimony,
however, established that this training was provided because the A-12 contract
was terminated, and was not attended by non-A-12 personnel. We cannot conclude
that these costs were not reasonable, allocable and allowable. These costs are
properly considered settlement expenses under FAR 31.205-42(g).
e. Non-Standard Overhead Rate
Coopers & Lybrand
disallowed $29,000 because McDonnell Douglas used "an incorrect rate for
nonstandard overhead applied to termination labor." Mr. Miller testified
that the use of that rate was not in compliance with the Cost Accounting
Standards (CAS) incorporated by FAR Part 31.
Mr. Cromer testified that
the $29,000 figure "represents the difference between the nonstandard
forecasted rate being applied at September '93 when the initial claim was
prepared, versus the year-end rate that was ultimately booked into the
accounting records." The correct rate was substituted for the non-standard
overhead rate in the 1997 update when the correct rates became available. We do
not question Mr. Cromer's credibility on this point.(16)
f. Robotic Paint and Assembly Pump
Coopers questioned
$2,978,763 in costs related to a robotic paint and assembly pump. Mr. Miller
testified that during the audit inquiry, McDonnell Douglas told the audit team
that costs associated with this robotic paint and assembly pump were to be
removed from the termination proposal because another program could use it.
Instead of removing these costs from its claim, however, McDonnell Douglas
increased the costs claimed for this equipment. The Government challenges these
costs as being related to common items that are disallowed under FAR
31.205-42(a). Miller's challenge is "based solely on his erroneous belief
that the sprayer could be used on another program," according to McDonnell
Douglas. Mr. Hancock testified that McDonnell Douglas tried to find a use for
the sprayer elsewhere -- for a while, it appeared that the sprayer could be
used in the F/A-18 program -- but ultimately no need for the sprayer arose.
This testimony was undisputed.
The costs associated with
the robotic paint sprayer are allowable, allocable and reasonable. Costs of
idle facilities are allowable if they are necessary when acquired and are idled
because of changes in requirements that could not reasonably have been
foreseen. See FAR 31.205-17.
8. Miscellaneous Costs
a. Computer Sciences Corporation --
Depreciation Charges
Coopers & Lybrand
challenged $54,879 "related to depreciation expenses of computer
equipment." The audit team sought documentation from General Dynamics
supporting these costs, but these efforts were unsuccessful, according to the
Government.
General Dynamics responds
that "the total amount of CSC depreciation was over $4 million, all but
$54,879 of which had been reconciled." General Dynamics contends that it
could have easily spent more than $54,000 trying to resolve the remaining
$54,000. This would have resulted in potential Government liability not only
for the $54,879 in depreciation, but also for the cost of the reconciliation
effort. Settlement expenses might include "[a]ccounting, legal, clerical,
and similar costs reasonably necessary for . . . [t]he preparation and
presentation, including supporting data, of settlement claims to the
contracting officer." FAR 31.205-42(g)(1)(i), (i)(A). Because the
Government did not assist with close-out of this contract, General Dynamics had
to determine on its own the proper level of expenditure to undertake to
substantiate its claims. See generally FAR 49.201(c).(17)
The Government challenges
only a small amount of CSC depreciation expense. Virtually all of the
depreciation was properly reconciled (almost 99%), and we agree with plaintiff
that chasing the remaining few dollars would not have been in the Government's
interest. The total amount claimed is allowable, allocable, and reasonable.
b. Retention Bonuses
Coopers challenged
$1,196,000 related to retention bonuses because it said that General Dynamics
did not have a "preestablished policy" for giving such bonuses. Mr.
Miller testified that retention bonuses were paid by General Dynamics to
non-General Dynamics employees.
FAR 31.205-6(a) provides, inter
alia:
Compensation for personal
services is allowable subject to the following general criteria and additional
requirements contained in other parts of this cost principle:
(3) The compensation must
be based upon and conform to the terms and conditions of the contractor's
established compensation plan or practice followed so consistently as to imply,
in effect, an agreement to make the payment.
The Government relies on
the wrong FAR provisions, according to General Dynamics. It had to retain
certain key employees to assist in contract close-out, to maintain program
security, and to assist with subcontractor settlements. The retention bonuses
for such purposes are awardable under FAR 31.205-42(g)(1)(i) - (iii), governing
post-termination settlement expenses. This section provides that such
settlement expenses are allowable, such as
(i) Accounting, legal,
clerical, and similar costs reasonably necessary for --
(A) The preparation and
presentation, including supporting data, of settlement claims to the
contracting officer; and
(B) The termination and
settlement of subcontracts.
(ii) Reasonable costs for
the storage, transportation, protection, and disposition of property acquired
or produced for the contract.
See also FAR 52.249-2(f)(3).
FAR 31.205-6(a) applies by
its terms only to payments made for services rendered during the period of
contract performance, General Dynamics argues. The provision applies only to
employees, rendering it inapplicable to those former General Dynamics employees
to whom the company paid retention bonuses. General Dynamics argues that even
if FAR 31.205-6 did apply, the applicable subsection would be FAR
31.205-6(f)(1). This subsection requires an established policy just as
31.205-6(f)(1) does, but General Dynamics maintains that it set up such an
established policy before paying any of the bonuses.
General Dynamics' argument
is persuasive. FAR 31.205-42(g)(1)(i) - (iii) appear to contemplate the
situation at hand. The Government benefitted from General Dynamics' retention
of key employees, at least indirectly. For example, Mr. Broesche negotiated
effectively with subcontractors, resulting in settlements for about half the
amount sought by the subcontractors. Although General Dynamics's argument that
it had an "established" policy of paying such bonuses is somewhat
tenuous, the decision to retain key employees served the best interests of the
Government as well as those of General Dynamics. We do not question that
judgment.
c. Loss of Useful Value-Material Transfer Credit
The audit team tested a
small sample of "transactions involving the transfer of A-12 equipment to
the F-16 program" for General Dynamics' "loss of useful value claim."
The auditors noted that General Dynamics transferred A-12 equipment to the F-16
program at less than net book value. Net book value at the time was $35,859.
The A-12 program was credited only $7,100. The audit team had concerns about
and questioned "the difference between the net book value of the item
transferred and the credit given to the A-12 program consistent with CAS 409
[Capitalization of Equipment]." The Government challenges $28,759 in
costs.
General Dynamics responds
that "the $28,759 in equipment was not A-12 equipment, but was
company-wide equipment charged to an indirect cost pool." It therefore
"would have been improper to credit the A-12 contract with costs
associated with its transfer because the value of the equipment (unlike the
value of the $7,068.82 in equipment that was credited to [the] government) had
never been charged to the A-12 contract, as Miller erroneously assumed."
The record before us does
not dispute General Dynamics' claim in this regard.
d. Certification Costs
General Dynamics charged
the Government $13,000 in certification costs for its updated termination for
convenience proposal," even though this proposal was not certified,
according to defendant. Coopers and Lybrand questioned the $13,000 claimed by
General Dynamics as unreasonable.
General Dynamics argues
that these costs are allowable settlement expenses under the FAR. See, e.g,
FAR 31.205-42(g)(1)(i)(A) (relating to costs necessary for preparing and
presenting settlement claims). It "expended these costs as part of a due
diligence review of the McDonnell Douglas portion of the termination for
convenience proposal." Mr. Wright testified that the claim of which the
Government complains was certified both by McDonnell Douglas and General
Dynamics after a review of their June 1991 termination for convenience claim.
We do not question these costs.
e. Unsettled Subcontractor Progress
Payments
Coopers & Lybrand
determined that $1,653,406 in costs "representing unliquidated progress
payments made to unsettled subcontractors" is still pending. "The
ultimate settlement of these remaining subcontractor claims could result in the
repayments of some or all of the outstanding unliquidated amount to General
Dynamics," according to the Government.
This challenge deals entirely
with unliquidated progress payments made to Harris Corporation. Mr. Wright, who
was involved in settlement negotiations with Harris at the time of trial,
testified that Harris is entitled to retain at least the $1,653,406 amount, and
perhaps more. This amount is not contingent or speculative, therefore, and it
is properly awarded to General Dynamics. Wright's testimony is undisputed. This
amount is awarded to General Dynamics.
IV.
YET TO BE INCURRED COSTS(18)
We ruled last year that
plaintiffs are entitled to reimbursement of costs that must be incurred in the
interest of national security. The "To-Go" portion of costs claimed
by General Dynamics for program security through June 1999 is estimated to be
$2,489,915. McDonnell Douglas' estimate is $1,910,416. These costs are awarded
pursuant to the earlier ruling. McDonnell Douglas has reached a settlement with
SCI since the time of trial.(19) Thus, $5 million is no longer a
cost yet to be incurred.
McDonnell Douglas'
obligation to pay General Dynamics $3.2 million for its efforts in building a
turntable is not contingent, and it is therefore included in the judgment.
McDonnell Douglas' claim for $2,367,175 for administrative / settlement
expenses is denied. Neither the $10,153,895 claimed by General Dynamics for
four unsettled subcontractors nor $246,072 claimed for settlement expenses is
allowable. We sustain defendant's challenge in the amount of $12,767,142.
CONCLUSION
Plaintiffs claim a total of
$3,992,455,272 in reasonable, allocable, and allowable costs. We established a
cap on plaintiffs' recovery of $3,499,793,515 for the FSED portion of the
contract. Adjusted for funds obligated through the IPR and EPA clauses, the
funding cap becomes $3,635,767,376. Adding the undisputed amounts of $.212
billion for Lot I and $.030 billion for Lot II, we arrive at $3,877,767,376.
The parties asked us to
rule on the total amount of plaintiff's reasonable, allowable and allocable
incurred costs, irrespective of the cap. The total amount of reasonable,
allowable and allocable costs incurred by plaintiffs is $3,978,002,676. The
judgment that we enter today, however, is $3,877,767,376.
The clerk will enter
judgment for plaintiffs in the amount of $3,877,767,376, plus statutory
interest from June 26, 1991 until paid. No costs.
________________________________
Robert H. Hodges, Jr.
Judge
1. FAR
52.249-9(g) is a fiction that has not operated smoothly in this case. A
contracting officer who has just terminated a contractor for default is not
interested in considering the same contractor's claim for termination for
convenience settlement costs. Nor is the contracting officer likely to
participate in subcontractor settlements as provided by FAR 49.108-7
("Government assistance in settling subcontracts"), if he assumes
that the contractors will be responsible for all of the subcontractor
settlements. That is what happened here. The contracting officer declined to
participate in the contractors' settlement discussions with subcontractors,
thereby giving plaintiffs an "estoppel" argument on that issue. We
did not address estoppel, but ruled that the settlements presumptively were
appropriate if the Government could not show collusion or less than arms-length
bargaining.
2. We
determined that the incremental funding clause (H-7) of the contract limits
plaintiffs' cost recovery to the funds obligated at the time of termination:
$3,499,793,515. See McDonnell Douglas Corp v. United States, 37
Fed. Cl. 295, 297 (1997), modified, No. 91-1204C, 1997 WL 766001 (Fed.
Cl. Dec. 5, 1997). When adjusted for funding obligated for Incentive Price
Revisions and Economic Price Adjustments (IPR/EPA), the total funding cap is
$3,635,767,376. See McDonnell Douglas Corp. v. United States, No.
91-1204C, 1997 WL 766001, at *8 (Fed. Cl. Dec. 5, 1997) (finding that
additional funding was obligated to cover approximately $135 million pursuant to
an Economic Price Adjustment Clause and an Incentive Price Revision Clause.)
Lots I and II were separate provisions in the A-12 contract that were not
governed by the incremental funding clause. Recovery under Lots I and II is not
in dispute. See McDonnell Douglas Corp., 37 Fed. Cl. at 297 n.2.
3. Under
the contract, plaintiffs were to produce eight FSED aircraft. The contract also
provided the Navy an option to purchase four production lots of aircraft. Each
FSED aircraft would test different characteristics of the A-12; stealth
capabilities would be verified in the "fully capable, fully equipped"
eighth aircraft that would serve as the basis for the production lots. Under
the original agreement, the first FSED aircraft would be delivered in June
1990; the rest would be delivered monthly through January 1991. The Navy
exercised its option on the first production lot on May 31, 1990. See
McDonnell Douglas Corp., 35 Fed. Cl. 358, 362 (1996).
4. 4
A note contained in the auditors' workpapers states the following: "Limit
the positive comments (actually none), we want 'negatives.' What is wrong with
the proposal."
5. 5
At the same time, we cannot fault Mr. Miller's emphasis on FAR Part 31. He is a
cost accountant, and he carried out the mission that he was given. He did not
have the access that he needed, and he was not provided other necessary tools
as plaintiffs generally claim.
6. 6
As General Dynamics argues in its post-trial brief:
"The fixed-price
nature of the contract provided the contractors with a financial incentive
during performance to incur only necessary costs, and to control strictly the
amount of those costs. . . . And, because the contract was terminated for
default, the contractors were liable, with no assurance of being reimbursed,
for all the amounts they incurred after termination, including all of the
amounts they paid to settle with their subcontractors."
Testimony at trial
supported this argument.
7. 7
The Government challenged costs as either "questioned" or
"pending." Questioned costs are considered by defendant not to be
reasonable, allowable, or allocable. Costs are designated "pending"
because the Government's audit team claims it did not have enough information
about them to make an evaluation. We reviewed all challenged costs on the same
basis.
8. 8
The Government determined that the impact of agreeing to pay Westinghouse $11
million in REAs is $10,098,968, after recomputing segregated loss ratios. We
stated that Westinghouse was entitled to a combined loss ratio, so the Government's
figure is incorrect. As we did not sustain this challenge, however, we need not
determine the actual impact of the payment.
9. 9
Wright had primary responsibility for the preparation of General Dynamics'
termination for convenience claim. A long-time employee of General Dynamics in
the financial cost accounting area, he had served as the deputy program
director of business management for the A-12 program since 1984. Allen
Broesche, John Lamers, and Ron Hancock also had worked on the A-12 program during
performance of the contract.
10. 10
Mr. Miller acknowledged, for example, that he did not know the first flight
date. He maintained that he did not necessarily need to know anything about the
contract schedule to challenge a cost related to an expediting charge.
12. Mr.
Cromer was McDonnell Douglas' manager of government accounting.
13. Cf.
P. Trueger, Accounting Guide for Government Contracts (10th ed. 1991) 713-25
(discussing court and board cases on recovery of unabsorbed overhead).
14. The
Government pressed Cromer on cross to explain why the $12.6 million in costs
were transferred:
Q: Okay. And prior to the
termination of the A-12 contract, where were those costs reflected?
A: They were reflected in
capital assets and then the depreciation went into overhead.
Q: So those costs were
allocated among all contracts at McDonnell Douglas, or at least government
contracts, including the A-12, right?
A: That is correct.
. . . .
Q: Can you explain why you
decided to move the costs out of the overhead pools to the A-12 termination?
A: Because that was our
policy at McDonnell Aircraft Company relative to assets that related to a
terminated contract.
Q: Can you tell me why you
did it, though? I mean, theoretically, what was the underpinning of that
decision?
A: The basis for that was
that these assets were acquired for a particular program, and they were
capitalized and depreciated. And when a program was terminated, it is part of
the cost associated with that program. I guess that's basically all I can
describe it as.
Q: But you would agree with
me, sir, that prior to the termination, even though the assets had been
acquired for a specific program, you were recovering those costs by charging
them to all contracts, A- 12 and others?
A: They were included in
the depreciation and the overhead expenses, yes, sir.
15. 15
General Dynamics provides the following additional explanation in its
post-trial brief:
At GD's Ft. Worth division,
a pool of people at one end of the factory waited to receive material, which
would pass through inspection and be delivered to the place on the factory
floor where it was needed. These expenses were incurred whether or not material
was being handled. GD divided the expenses for this labor between the various
contracts at the Ft. Worth division. To divide the costs between the contracts,
a "base" was established, and a rate that was negotiated with the ACO
was applied to the base to determine the amount to be charged to each contract.
The base that GD used for all of its contracts, including the A-12, included
both liquidated and unliquidated progress payments. GD had used this method for
years, with disclosure to, and approval by, the government.
. . . .
Nevertheless, [Coopers]
challenges the use of this method because it appears to allow GD to recover
material handling on materials -- represented by unliquidated progress payments
-- that were never handled. This challenge ignores the fact that the base is
merely a method to estimate the proper allocation of actually incurred overhead
between various contracts. The challenge in fact would have the effect of
denying GD reimbursement of material handling expenses actually incurred.
Because GD -- with full knowledge and approval of the government -- divided its
pool of costs among its various contracts using a calculation that included
unliquidated progress payments, removal of those payments from the A-12 base
after the fact would result in underestimating the A-12 contract's pro rata
share of those actually incurred expenses. The government cannot retract
retroactively its approval of a contractor's established accounting method to
the detriment of the contractor. See Litton Systems, Inc. v. United States,
449 F.2d 392, 394, 399-401 (Ct. Cl. 1971).
16. Additional
testimony provided as follows:
Q: When the 1994 update was
prepared, it used September 1993 data?
A: That is correct.
Q: And as of September
1993, were there final nonstandard overhead rates for the year 1993?
A: No, there was not.
Q: Are there currently
rates for 1993 like that?
A: Yes, there are.
Q: Final rates?
A: Yes.
Q: Are there also final
rates for 1994, '95 and '96?
A: Yes, there are.
Q: Are those final rates
used in the 1997 update?
A: The final nonstandard
overhead rate is used for all of those years, yes.
18. 18
Defendant notes in its post-trial brief:
The Government challenges
plaintiffs' claim for approximately $26 million in contingent costs not yet
incurred. These contingent costs are primarily for program security costs,
settlement expenses, and settlement with remaining subcontractors. These costs
are unallowable. "Pursuant to FAR 52.249-2. Termination for Convenience of
the Government (Fixed-Price) the contractor may recover costs incurred in the
performance of the work." Sterling Millwrights, Inc. v. United States,
26 Cl. Ct. 49, 112 (1992) (emphasis added). Moreover, cost principles expressly
prohibit, in FAR Part 31, recovery of non-incurred, contingent costs. See
FAR 31.205-7(a) and 7(b).
19. 19 McDonnell Douglas
agreed to pay $8 million pursuant to the settlement, but its claim remains $5
million.
98-5096,-5122,5123
MCDONNELL
DOUGLAS CORPORATION,
Plaintiff-Cross
Appellant,
and
GENERAL
DYNAMICS CORPORATION,
Plaintiff-Cross
Appellant,
v.
UNITED
STATES,
Defendant-Appellant.
Bruce J. Ennis, Jr., Jenner & Block, of
Washington, DC, argued for plaintiffs-cross-appellants. With him on the brief
were David W. DeBruin and Deanne E. Maynard. Also on the brief were Caryl A.
Potter, III and Elizabeth A. Ferrell, Sonnenschein Nath & Rosenthal, of
Washington, DC. Of counsel on the brief were John W. Walbran, McDonnel Douglas
Corporation, of Berkeley, Missouri; Herbert L. Fenster and David A. Churchill,
McKenna & Cuneo, L.L.P., of Washington, DC; and Edward C. Bruntrager,
General Dynamics Corporation, of Falls Church, Virginia.
Mark B. Stern, Attorney, Appellate Staff, Civil
Division, Department of Justice, of Washington, DC, argued for defendant-appellant.
With him on the brief were Stephen W. Preston, Deputy Assistant Attorney
General; David M. Cohen, Director, and Bryant G. Snee, Assistant Director,
Commercial Litigation Branch; and Jacob M. Lewis, Thomas M. Bondy, Michael S.
Raab, and H. Thomas Bryon, III, Attorneys, Appellate Staff. Of counsel on the
brief was George P. Williams, Special Counsel for Litigation, Office of General
Counsel, Department of the Navy, of Arlington, Virginia.
Appealed from: United States Court of Federal Claims
Judge Robert H. Hodges, Jr.
United States Court of Appeals for the Federal
Circuit
98-5096, -5122, -5123
MCDONNELL DOUGLAS CORPORATION,
Plaintiff-Cross Appellant,
and
GENERAL DYNAMICS CORPORATION,
Plaintiff-Cross Appellant,
v.
UNITED STATES,
Defendant-Appellant.
___________________________
DECIDED: July 1, 1999
___________________________
Before MAYER, Chief Judge, MICHEL and CLEVENGER,
Circuit Judges.
CLEVENGER, Circuit Judge.
This dispute arises out of the government's default
termination of a contract between the United States Navy and defense
contractors McDonnell Douglas Corporation and General Dynamics Corporation
("Contractors") to develop a carrier-based, low-observable
"stealth" aircraft known as the A-12 Avenger. After several years of litigation,
the United States Court of Federal Claims held that the government's
termination of the contract for default could not be sustained because the
government did not exercise the requisite discretion before entering a default
termination, see McDonnell Douglas Corp. v. United States, 35 Fed. Cl. 358,
368-71 (1996) (hereinafter McDonnell Douglas IV), and converted the termination
for default into a termination for convenience, awarding Contractors costs
totaling $3,877,767,376. See McDonnell Douglas Corp. v. United States, 40 Fed.
Cl. 529, 555-56 (1998) (hereinafter McDonnell Douglas IX). We hold that,
because the termination for default was predicated on contract-related issues,
it was within the discretion of the government. Accordingly, the Court of
Federal Claims' conversion of the termination for default into a termination
for convenience was in error. We reverse the trial court's judgment and remand
the case to the trial court for a determination of whether the government's
default termination was justified, an issue upon which we express or intimate
no view.
I
A
In 1984, the Department of the Navy introduced the
Advanced Tactical Aircraft Program, known as the A-12 program, to develop a
carrier-based stealth aircraft for the Navy. In January 1988, Contractors
entered into a Full Scale Engineering Development contract (the "A-12 FSD
Contract") with the government to produce eight FSD aircraft at a target
price of $4,379,219,436. See McDonnell Douglas IV, 35 Fed. Cl. at 361. The contract
was structured as an incrementally funded, fixed-price incentive contract with
a ceiling price of $4,777,330,294, and recited a schedule of installment
payments over the five-year term of the contract. The first aircraft was
originally scheduled to be delivered in June 1990, and subsequent aircraft were
to be delivered each month through January 1991. See id. at 361-62.
From the outset, Contractors encountered difficulties
in performing the contract. Particular problems included meeting the contract
schedule and keeping the aircraft weight within specifications. At the
beginning of 1990, the Department of Defense initiated a Major Aircraft Review
to evaluate various major aircraft programs in view of recent changes around
the world and the corresponding reduced threat to national security. See id. at
362. The A-12 program was included in this Review, and Defense Secretary
Richard Cheney visited the McDonnell Douglas plant as part of the review
process. By the early part of 1990, the Navy's contracting officer knew that
Contractors would not meet the delivery date for the first aircraft. See id.
However, although Secretary Cheney was apprised of some concerns in the A-12
program, the review concluded that there was a continuing need for the A-12 and
that the Navy should pursue the program. See id. at 363. Secretary Cheney
reported these results during his testimony before Congress in April 1990.
In June 1990, Contractors informed the Navy that they
could not meet the contract schedule, that the cost of completing the contract
would substantially exceed the ceiling price, and that Contractors could not
absorb the loss that would result from the contract. Contractors asserted that
a fundamental problem with the FSD contract was its structure as a fixed-price
contract and proposed that the contract be modified. Thereafter, Contractors
submitted a proposal to change the contract schedule, but the Navy and
Contractors failed to reach an agreement on that issue. Instead, on August 17,
1990, the Navy unilaterally issued a contract modification that changed the
delivery schedule for the aircraft. Under this modification, the delivery date
of the first aircraft was delayed until December 1991, and the remaining
aircraft became due periodically between February 1992 and February 1993. See
Contract Modification P00046 1(b), Joint Appendix at 15,657.
In November 1990, Contractors submitted a formal
request to the Navy to restructure the contract as a cost-reimbursement type
contract. At the end of the same month, two reports were published which
documented the handling of the A-12 program under the Major Aircraft Review.
The Navy's "Beach Report," dated November 28, 1990, found that the
A-12 program manager had been unreasonable both in reaching a conclusion that
the contract could be performed within the ceiling price and in evaluating the
risk of failing to meet the contract schedule. See McDonnell Douglas IV, 35
Fed. Cl. at 363. The Beach Report criticized several Navy officials involved in
the A-12 program. Separately, a November 29, 1990 Department of Defense
Inspector General report concluded that problems in the A-12 program were
inaccurately identified during the Review because the Review did not accord
with specified procedures and was otherwise handled poorly. See id.
During the Secretary's briefing to the President of
the United States in early December 1990, the Secretary indicated his
disappointment with the Navy's handling of the A-12 program and promised to
take appropriate actions. On December 3, the Secretary directed the Deputy
Secretary of Defense to review and report on the status of the A-12 program
within ten days. This resulted in several meetings by the Defense Acquisition
Board and Defense Procurement Review Boards. In addition, on December 12, the
Secretary of the Navy responded to Secretary Cheney's December 3 request with a
memorandum that expressed concern about Contractors' ability and willingness to
perform under the contract, and which noted in particular Contractors' belief
that the government should assume responsibility for failure to meet goals
under the contract, and that the government should restructure the contract.
The memorandum concluded with a statement that the Navy would examine whether
the contract should be terminated for default, and would make a recommendation
to the Secretary by January 5, 1991. See id.
On Friday, December 14, Secretary Cheney directed the
Secretary of Navy to show cause by January 4, 1991 why the A-12 program should
not be terminated. The following Monday, December 17, the Navy issued a cure
notice to Contractors stating that unless they were able to meet contract
specifications by January 2, 1991, the government might choose to terminate the
contract for default. In particular, the cure letter stated that, inter alia, Contractors
had "failed to fabricate parts sufficient to permit final assembly in time
to meet the schedule for delivery," and had "fail[ed] to meet
specification requirements." Joint Appendix at 16,524. The letter asserted
that "[t]hese conditions are endangering performance of [the]
contract." Id.
High-level meetings between the responsible
government personnel, including the contracting officer and the general
counsels of the Department of Defense and of the Navy, and Contractors,
including the Chief Executive Officers of McDonnell Douglas and General
Dynamics, occurred on December 18 and 21. During these meetings, Contractors
asserted that they "[c]an't get there if we don't change contract,"
id. at 16,533, and "[i]t has got to get reformed to a cost type contract
or we cannot do it." Id. at 16,549. When asked by the government on
December 21 "can you correct deficiencies to provide an aircraft that
meets the requirements," Contractors replied "[a]ll deficiencies
cannot be corrected. Can we deliver a satisfactory aircraft for the Navy?
Mother nature won't allow correction of all defects. We'll do the best we can
and the Navy has to decide if that's good enough." Id. at 16,548-49.
Contractors responded to the cure notice on January 2
by admitting that they "[would] not meet delivery schedules or certain
specifications of the original contract, or the revised FSD delivery
schedule." Id. at 18,175. Contractors did not contest that they had failed
to fabricate parts in time to meet the delivery schedule for the FSD aircraft.
Nonetheless, Contractors asserted that they were not in default because, in
their view, the delivery schedules were invalid or unenforceable. See id. at
18,175-78. As suggested cure, Contractors submitted a proposal to restructure
the contract, pursuant to which Contractors would absorb a $1.5 billion fixed
loss on the cost overrun from the contract, the contract would be restructured
to a cost reimbursement contract, and Contractors would waive their claims for
equitable adjustment. Contractors proposed to restructure the contract pursuant
to Pub. L. No. 85-804, which gives the President of the United States the power
to authorize departments or agencies connected with national defense to grant
extraordinary relief under contracts if such an action facilitates the national
defense. See 50 U.S.C. 1431 (1994).
On Saturday, January 5, Secretary Cheney met with
Undersecretary of Defense for Acquisition Yockey, the Secretary of the Navy,
and the Chairman of the Joint Chiefs of Staff to discuss the budget and the
A-12 program. At the meeting, Secretary Cheney noted that a scheduled payment
of $553 million--one of the largest installment payments under the A-12
contract--was due on Monday, January 7. Later that day, Secretary Cheney,
acting under authority pursuant to Pub. L. No. 85-804, decided not to grant
relief. On Sunday, January 6, Undersecretary Yockey informed Rear Admiral
William R. Morris, who at this time was acting as contracting officer over the
A-12 contract, that Secretary Cheney had denied 85-804 relief and that no
further funds would be obligated under the A-12 program. The next day, Admiral
Morris issued the termination letter to Contractors stating that the government
was terminating the A-12 contract due to Contractors' default.
B
On February 5, 1991, the Navy sent a letter to
Contractors demanding the return of approximately $1.35 billion in unliquidated
progress payments under the terminated contract. On June 7, Contractors filed
suit in the United States Court of Federal Claims under the Contract Disputes
Act, 41 U.S.C. 609(a) (1994), requesting that the court: (1) grant their
equitable adjustment claims dated December 31, 1990, (2) convert the
government's termination for default into a termination for convenience, (3)
deny the government's demand for return of progress payments, (4) award
Contractors costs and a reasonable profit under the contract, (5) award them
settlement expenses, and (6) award damages for breach of contract. See
McDonnell Douglas Corp. v. United States, 25 Cl. Ct. 342, 346 (1992).
After several years of litigation in the Court of
Federal Claims, that court ruled, in a decision dated April 8, 1996, that the
government's default termination was invalid according to Schlesinger v. United
States, 390 F.2d 702 (Cl. Ct. 1968). See McDonnell Douglas IV, 35 Fed. Cl. at
368-71. The trial court held that under Schlesinger, the government is required
to exercise "reasoned discretion" before terminating a contract for
default, and that the government failed to meet this requirement because the
Secretary of Defense's actions effectively forced the Navy to terminate the
A-12 contract for default. See id. at 369-71. Therefore, the trial court
vacated the government's termination for default and converted it into a termination
for convenience. See id. at 361.
In further litigation over damages, Contractors
claimed that they were entitled to recover a reasonable profit under the
contract, whereas the government argued that any recovery should be reduced by
an appropriate loss-adjustment ratio. Contractors further alleged that the
government possessed knowledge regarding how difficult it would be to perform
the A-12 contract, and that under the "superior knowledge" doctrine,
the government had a duty to either disclose such knowledge or otherwise
protect Contractors against suffering unreasonable losses under the contract.
The court held that the government's claim for a loss adjustment, Contractors'
claim for reasonable profits, and the superior knowledge claim could not be further
litigated because of the government's invocation of the "state secrets
doctrine," see McDonnell Douglas Corp. v. United States, 37 Fed. Cl. 270,
272 (1996) (hereinafter McDonnell Douglas V), which grants the Executive the
exclusive right to bar discovery into specific classified areas that affect
state secrets. See United States v. Reynolds, 345 U.S. 1, 7 (1953). The court
ultimately denied the government's claim for return of $1.35 billion in
unliquidated progress payments, and allowed Contractors total costs under the
contract of approximately $3.88 billion. Taking into account progress payments
of some $2.68 billion that had already been paid to Contractors, the court
entered judgment of approximately $1.2 billion in favor of Contractors. See
McDonnell Douglas IX, 40 Fed. Cl. at 555-56.
The government appeals from the trial court's
decision to convert the default termination to a termination for convenience,
and from the trial court's refusal to apply a loss-adjustment ratio in
calculating damages. Contractors conditionally cross-appeal the trial court's
ruling, arguing that the government has no power to terminate an
incrementally-funded contract for failure to make progress toward a goal that
has not yet been funded. Contractors also assert that their recovery cannot be
reduced by a loss-adjustment factor based on the estimated cost of completing
work that was never funded. We have jurisdiction pursuant to 28 U.S.C.
1295(a)(3).
II
The level of discretion that must be exercised by the
government before terminating a contract for default is a question of law,
which we review de novo. See Darwin Constr. Co. v. United States, 811 F.2d 593,
596 (Fed. Cir. 1987); Barseback Kraft AB v. United States, 121 F.3d 1475, 1479
(Fed. Cir. 1997). We will upset the trial court's factual findings, however,
only if they are clearly erroneous. See, e.g., Bass Enters. Prod. Co. v. United
States, 133 F.3d 893, 895 (Fed. Cir. 1998).
A
The trial court held that the government's
termination of the A-12 contract did not comport with the rule laid down in
Schlesinger by the United States Court of Claims, our predecessor court, for a
proper default termination. Schlesinger involved a cap manufacturer who won a
contract to supply the Navy with 50,000 service caps for enlisted men. The
contract required the manufacturer to submit pre-production samples of
component materials, as well as two samples of the completed cap, to the
government for approval prior to production. In addition, the contract included
a delivery schedule which set forth delivery dates for five separate
installments of the completed caps. See Schlesinger, 390 F.2d at 703-04.
Schlesinger did not submit the two sample caps and certain thread for
pre-production approval, perhaps because he had fulfilled a contract for
240,000 identical Navy caps the previous year. Schlesinger also failed to
deliver the first installment of caps as specified in the delivery schedule.
See id. At the time, Schlesinger was also a prime suspect in an ongoing United
States Senate subcommittee investigation regarding textile procurement
irregularities within the military. Indeed, Schlesinger testified before the
subcommittee during the pendency of his supply contract; shortly after his
testimony, the chairman of the subcommittee sent a letter to the Navy implying
that Schlesinger's contract should be terminated. This information was
communicated to the contracting officer, who promptly terminated Schlesinger's
contract. See id. at 705-06.
The Court of Claims held that the default termination
of Schlesinger's contract was illegal. In doing so, the court first found that
Schlesinger was indeed technically in default under the terms of the contract.
See id. at 706-07. However, the court determined that neither the contracting
officer nor anyone else in the Navy exercised independent judgment in
terminating the contract for default. See id. at 707-08 (citing John A. Johnson
Contracting Corp. v. United States, 132 F. Supp. 698, 704-05 (Ct. Cl. 1955)).
Thus, the court found that the contractor's "bare" or
"technical" default "served only as a useful pretext for the
taking of action felt to be necessary on other grounds unrelated to the
[contractor's] performance . . . ." Id. at 709.
The illegality in Schlesinger stemmed from the Navy's
reliance on contractor default as a pretext to terminate its relationship with
the contractor, independent of the state of actual performance under the
contract. The court characterized Schlesinger's performance shortcomings as
merely a "technical default" or "bare default," id. at 707,
708, and emphasized the Navy's total failure to consider the level of
performance once it found a means for terminating by default. See, e.g., id. at
708 ("[T]he Navy acted as if it had no option but to terminate for default
. . . once the mere fact of non-delivery was found."). In Schlesinger, it
was improper for the Navy to terminate the contractor for default due solely to
pressure from a congressional oversight committee because this ground for
termination was totally unrelated to contract performance.
In short, Schlesinger bars only a termination for
default in which there is no considered nexus between the default termination
and the contractor's performance under the contract. A second case relied upon
by Contractors, John A. Johnson Contracting Corp. v. United States, 132 F.
Supp. 698 (Ct. Cl. 1955), also supports this rule. In Johnson, the plaintiff
contractor failed to complete construction for Army hospital buildings in a
timely fashion because of bad weather that had rendered certain construction
roads unusable. The construction roads had previously been contracted out to a
different contractor. See id. at 699-700. After numerous delays, the
contracting officer determined that both the roads and buildings should be
completed by a single contractor, and therefore decided to terminate the
plaintiff's contract. Although the contracting officer intended to terminate
the plaintiff's contract for convenience, he ultimately terminated the contract
for default because government lawyers informed him that a nondefault
termination would create legal problems. See id. at 705. Because the Johnson
court found that the contracting officer had already decided to terminate the
plaintiff for convenience, it held that the change to a termination for default
"did not represent [the contracting officer's] judgment as to the merits
of the case." Id. Indeed, because the court found, as a factual matter,
that the plaintiff could not be held at fault for the unforeseen conditions,
see id. at 703-04, there could be no proper nexus between a termination for
default and the plaintiff's performance.
A third case cited to us by Contractors, Darwin
Construction Co. v. United States, 811 F.2d 593 (Fed. Cir. 1987), further
confirms the rule identified above. In Darwin, we adopted the Armed Services
Board of Contract Appeals's finding that "the default action was taken
solely to rid the Navy of having to deal with Darwin." Id. at 596
(internal quotation marks omitted). Thus, we held that the government used Darwin's
technical default as a mere pretext for terminating the contract on grounds
unrelated to performance. See id. Furthermore, Darwin clarifies what is meant
by the "reasonable discretion" test used in Schlesinger and Johnson.
In Darwin, we stated that, although a contracting officer has discretion with
respect to contract termination, a termination for default will be set aside if
it is arbitrary or capricious, or constitutes an abuse of the contracting
officer's discretion. See id. at 598. When there is no nexus between the
decision to terminate for default and contract performance, as was true in
Darwin, Schlesinger, and Johnson, the termination for default may be arbitrary
and capricious and set aside in favor of a termination for convenience.
Properly understood, then, Schlesinger and its
progeny merely stand for the proposition that a termination for default that is
unrelated to contract performance is arbitrary and capricious, and thus an
abuse of the contracting officer's discretion. This proposition itself is but
part of the well established law governing abuse of discretion by a contracting
official. See, e.g., United Sates Fidelity & Guaranty Co. v. United States,
676 F.2d 622, 630 (Ct. Cl. 1982) (listing four factors to be used in determining
if conduct by a government official is arbitrary and capricious: (1) evidence
of subjective bad faith on the part of the government official, (2) whether
there is a reasonable, contract-related basis for the official's decision, (3)
the amount of discretion given to the official, and (4) whether the official
violated an applicable statute or regulation).
B
The record shows that the government's default
termination was not pretextual or unrelated to Contractors' alleged inability
to fulfill their obligations under the contract. Therefore, unlike the cases
cited above, the government's decision to terminate the A-12 FSD Contract for
default was related to contract performance, and the Court of Federal Claims
erred by converting the termination into one for convenience without first
addressing the question of breach.
First, the trial court interpreted the Navy's actions
prior to termination to evince a desire not to terminate the A-12 program for
default, but rather to continue the contract. See McDonnell Douglas IV, 35 Fed.
Cl. at 370. For example, the trial court noted that the government had
overlooked Contractors' alleged default for several months, had unilaterally
modified the contract to excuse the missed delivery date for the first
aircraft, and had determined that even though the aircraft would be overweight,
it would still meet operational requirements. See id. 370, 373-74. Moreover,
the trial court noted that the Navy "did not contemplate issuing a cure
notice in December [1990]" and "did not believe the contractors'
performance justified termination." Id. at 370.
The trial court's factual findings do in fact
establish that the Navy did not want to terminate the A-12 program. Instead, at
all times up until the very end, the Navy hoped to preserve the program and its
A-12 aircraft. That is not to say, however, that Contractors were not in
default under the contract, or that the government did not have the right to
terminate the contract for default. A party to a contract, faced with a breach
by the opposing party, can choose either to terminate the contract or to
continue the contract, perhaps extracting other concessions or consideration
from the breaching party in return for its willingness to modify the contract.
See, e.g., 3 Samuel Williston & Richard A. Lord, A Treatise on the Law of
Contracts 7:36 (4th ed. 1992). A party that chooses to proceed with the
contract--even if it is the government, and even if it manifests a strong
desire to procure the item that is the subject of the contract--does not thereby
waive its right to terminate for default. Indeed, the trial court's finding
that the Navy went to great lengths to preserve the A-12 program suggests that
it would not have terminated the contract but for its belief that Contractors
had breached the contract or would not perform the contract.
More importantly, however, the record demonstrates
that the government properly terminated the A-12 program for reasons related to
contract performance. Admiral Morris, the contracting officer, testified at
length about his decisional process that led to the termination for alleged
default. He thought that he had three choices: to terminate for convenience, to
terminate for default, or to do nothing. He rejected the latter as
"irresponsible," thus focusing his attention on the other two
choices. He eliminated the termination for convenience first, because he
believed Contractors to be in material breach of the contract. This was so, in
his words, because, as conceded in Contractors' response to the cure notice:
They were in default because they acknowledged they
would not be able to achieve the contract specifications and the contract
requirements. Two, they had indicated that the would not be able to meet the
delivery schedule that was currently in the contract. And three, they would not
be able to perform the contract without extraordinary relief or additional
funding for the contract. So they basically said they can't perform under the
contract and they were in default of it.
Joint Appendix at 3,898-99. In further elaboration of
his decision, again in the context of Contractors' response to the cure notice,
Admiral Morris testified as to why he thought Contractors' default was
material:
They had failed to fabricate parts so as to endanger
performance of the contract, and in my judgment, as would relate to the
production options, failed to make progress, and it was clear to me that that
is where they stood on the 7th of January when I terminated the contract for
default.
Id. at 3,917. As to why a termination for convenience
was inappropriate, Admiral Morris stated that:
[B]ecause I felt very strongly that as a result of
the contractors' default, it would be nothing short of unconscionable for me to
put the burden of the contractors' failure to make progress and the
contractors' failure to fabricate parts, so as to endanger performance of the
contract, put that burden on the government and the taxpayer to reimburse all
costs and to pay the contractors a profit for their failures.
Id. at 3,920. Therefore, Admiral Morris terminated
the contract for failure to make progress and for failure to meet contract
requirements.
Failure to meet contract specifications and inability
to meet the contract delivery schedule are of course relevant considerations to
whether a contractor is in default. See Discount Co. v. United States, 554 F.2d
435, 441 (Ct. Cl. 1977) (inability to meet specifications); Universal
Fiberglass Corp. v. United States, 537 F.2d 393, 398 (Ct. Cl. 1976) (failure to
meet schedule); see generally John Cibinic, Jr. & Ralph C. Nash, Jr.,
Administration of Government Contracts 929-35 (3d ed. 1995) (discussing the
requirements for a default termination based on failure to make progress); id.
at 953-60 (discussing anticipatory repudiation by a contractor, such as "nonperformance
and claims for payments or relief from matters as to which the contractor had
assumed the risk").
The trial court also found that Secretary Cheney
denied extraordinary relief, which led to the termination, because of concerns
about the A-12 program's "cost and schedule." McDonnell Douglas IV,
35 Fed. Cl. at 372. The cost to complete a contract--more particularly, the
inability of a contractor to perform a contract at the specified contract
price--and the ability to meet a contract schedule are both fundamental
elements of government contracts and are related to contract performance; as
such, they are highly relevant to the question of default.
The government had specific concerns about when--and
if--the A-12 aircraft would ever be delivered and how much it would cost.
Secretary Cheney stated in testimony before Congress that the A-12 program was
terminated because "no one could tell me how much the program was going to
cost even just through the full-scale development phase or when it would be
available. Data that had been presented at one point a few months ago turned
out to be invalid and inaccurate." Hearings on National Defense
Authorization Act for Fiscal Years 1992 and 1993 -- H.R. 2100 and Oversight of
Previously Authorized Programs Before the House Comm. on Armed Servs., 102nd
Cong. 60 (1991) (statement of Richard Cheney, Secretary of Defense). The
evidence in the record demonstrates that the Secretary of Defense denied relief
under Pub. L. 85-804, and Admiral Morris chose to terminate the contract for
default, for reasons related to Contractors' state of performance of the
contract. The trial court emphasized that although Contractors failed to meet
the aircraft weight limit, the Navy essentially waived this requirement because
the overweight aircraft would still meet all operational requirements. See
McDonnell Douglas IV, 35 Fed. Cl. at 363, 376. However, although that finding
is relevant to the ultimate determination of whether Contractors were in
breach, or whether a breach was excused, it is insufficient to show, in light
of all the other evidence in the record, that the government terminated the
contract for reasons wholly unrelated to contract performance.
We think it clear beyond any doubt that Admiral
Morris, unlike the contracting officer in Schlesinger, or in other cases that
have upset terminations for default for lack of nexus to contract performance
behavior, made his choice for reasons related to contract performance. Admiral
Morris certainly knew that Contractors took another view of events transpiring
during contract performance: although they admitted that they could not perform
the contract according to its terms, they felt that the fault for their failure
should be laid at the government's feet. Admiral Morris meant not to take away
the right of Contractors to assert their defenses to termination for default,
he instead only meant to assert the government's right to allege material
breach on the record of contract performance that had been laid before him by
Contractors themselves. Given the reasons stated for the action taken by the
contracting officer in this case, it was legal error for the trial court to see
these facts as commanding conversion of the termination for default into one
for the convenience of the government.
To summarize, the government may not use default as a
pretext for terminating a contract for reasons unrelated to performance;
instead, there must be a nexus between the government's decision to terminate
for default and the contractor's performance. The record and the facts found by
the trial court establish that the government denied additional funding for the
A-12 program and terminated the contract for default because of concerns about
contract specifications, contract schedule, and price--factors that are
fundamental elements of contract performance. Therefore, the trial court erred
by vacating the termination for default without first determining whether a
default existed. On remand, if the government can establish that Contractors
were in default, then the termination for default would be valid. See Lisbon
Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987) (holding
that the government bears the burden of proof with respect to the issue of
whether termination for default was justified). Conversely, if the government
is not able to make this showing, then the default termination was invalid and
Contractors would be entitled to a suitable recovery, presumably under a
termination for convenience theory.
III
We turn next to the government's argument that the
trial court erred in refusing to apply a loss ratio to Contractor's termination
for convenience recovery, and the trial court's related treatment of
Contractors' claims under the superior knowledge theory and for reasonable profits.
In government contracts law, under certain circumstances the government owes a
duty to disclose critical information to a contractor that is necessary to
prevent the contractor from unknowingly pursuing "a ruinous course of
action." Helene Curtis Indus., Inc. v. United States, 312 F.2d 774, 778
(Ct. Cl. 1963). This doctrine of superior knowledge is well established in law,
see, e.g., Hardeman-Monier-Hutcherson v. United States, 458 F.2d 1364, 1371-72
(Ct. Cl. 1972); Helene Curtis Indus., 312 F.2d at 778 & n.1, and failure to
disclose crucial information can lead to a finding of contract breach by the
government, see, e.g., GAF Corp. v. United States, 932 F.2d 947, 949 (Fed. Cir.
1991). In this case, the government resisted Contractors' superior knowledge
claims on the ground that the government could not have an implied duty to
reveal classified information pertinent to the A-12 program that would threaten
national security. The trial court denied the government's motion to dismiss
the superior knowledge claims on the pleadings and allowed Contractors limited
discovery. See McDonnell Douglas V, 37 Fed. Cl. at 275-76.
After a series of security breaches and discovery
abuses, the trial court concluded that it could not litigate further the
related issues of loss adjustment, superior knowledge, and reasonable profits.
See id. at 272, 276-78. Contractors do not directly appeal this ruling; they
contend only that if we upset the trial court's decision on loss adjustment, a
remand of all three is appropriate. The government argues that Contractors'
superior knowledge and reasonable profits claims were properly removed from
litigation because they jeopardized state secrets, but that its loss adjustment
claim could be litigated without this danger and should have been allowed to
proceed. Because we conclude that the trial court erred in converting the
government's default termination of the A-12 FSD Contract to a termination for
convenience, whether a loss adjustment applies to termination for convenience
damages is not ripe for our decision. Because of the passage of time and of
possible intervening developments, we are in no position to judge whether the
risk of disclosure of state secrets will preclude adjudication, on remand, of
Contractors' superior knowledge claim, and the issues of loss adjustment and
reasonable profit. We think the trial court must be free to adjudicate the
government's defense of its termination for default in the manner most fair and
just to the parties. The trial court thus is free to reconsider this issue on
remand. We express no view on the trial court's previous ruling on whether
these three interrelated issues may be litigated.
IV
Turning finally to Contractors' cross-appeal, we
consider whether the nature of the A-12 contract as a fixed-price,
incrementally-funded contract affects the government's ability to terminate the
contract. Contractors first argue that the government cannot apply a loss
adjustment factor, based on the estimated cost of completing the contract, to
Contractor's recovery under a termination for convenience because the
government was not obligated to fund the contract to completion. Because we
reverse the trial court's conversion of the default termination to a
termination for convenience, we do not address this point.
Contractors similarly argue that the government
cannot legally terminate the A-12 FSD Contract for failure to make progress
toward work that the government was not obligated to fund, and which it in fact
did not fund in full. Contractors argue that because the government limited its
potential liability to Contractors through the incremental funding arrangement,
see A-12 FSD Contract, H-7(c), Joint Appendix at 15,073, there was no mutuality
of obligation for the full FSD contract, and the contract was only valid to the
extent of the funds already obligated. Under Contractors' theory, it follows
that the government could not terminate the contract for failure to make
progress toward work that they were not legally obligated to perform. In
essence, Contractors assert that the government was precluded from terminating
them for default due to failure to make progress toward the completion of the
A-12 contract, unless and until the government had funded the contract in full.
We reject Contractors' arguments, however, for the
following reasons. First, the A-12 FSD Contract explicitly recites the grounds
upon which the government may terminate the contract for default, which grounds
include Contractors' failure to make progress. See 48 C.F.R. 52.249-9(a)(1)(ii)
(1984); A-12 FSD Contract I I, Joint Appendix at 15,251 (incorporating FAR
52.249-9). Contractors agreed to installment funding of the contract because
the government could not obligate the full ceiling price at the time of
contracting. See id. H-7(a), Joint Appendix at 15,072. In order to comply with
the Anti-Deficiency Act, see 31 U.S.C. 1341(a) (prohibiting expenditures,
obligations, and contracts exceeding appropriations), the parties specified
that the government's total obligation, including termination costs, would
never exceed the amount obligated at the time of termination. See A-12 FSD
Contract H-7(c), Joint Appendix at 15,073. In return, Contractors were not
required at any time to incur costs in excess of the total obligated amount.
See id. H-7(b), Joint Appendix at 15,072. Despite this funding arrangement,
however, the parties agreed that the government had the right to
"terminate this contract in whole or in part if the Contractor fails to .
. . [p]rosecute the work so as to endanger performance of this contract."
48 C.F.R. 52.249-9(a)(1)(ii) (1984). Therefore, installment funding did not
contractually manifest itself as a condition to Contractors' performance; it
merely stated a term characterizing the performance of the government. Moreover,
the terms of the contract make clear that failure to make progress was a valid
basis for default termination.
Second, we disagree with Contractors regarding their
obligations under the A-12 FSD Contract. Contractors emphasize that, because of
the incremental funding, there has never been a binding contract for completion
of full FSD performance. Contractors acknowledge that the government could have
default terminated the contract for failure to meet specific requirements
associated with a particular installment of funding, but assert that failure to
meet such specific requirements constitutes the only basis for a valid default
termination. Because the contract did not link any specific objectives to a
particular level of funding, Contractors argue, there was no basis for a
default termination. We agree with Contractors that, at the time of
termination, they were not obligated to complete all contract requirements.
That does not mean, however, that Contractors did not have any obligations with
respect to the full FSD requirements. As we noted above, the A-12 FSD Contract
recites failure to make progress as a basis for contractor default and contract
termination. See 48 C.F.R. 52.249-9(a)(1)(ii) (1984). Therefore, Contractors'
assertion that failure to meet contract requirements that are linked to
already-funded work is the sole basis for default is simply incorrect. Failure
to satisfy such requirements forms a ground for default under 48 C.F.R.
52.249-9(a)(1)(i) (stating that the government may terminate a contract for
default if the contractor fails to "[p]erform the work under the contract
within the time specified in this contract or any extension"). Subsection
(a)(1)(ii), in contrast, provides a separate basis for default: it obligates
Contractors to make enough progress so that contract performance is not
endangered. See Universal Fiberglass Corp., 537 F.2d at 398 (Ct. Cl. 1976)
("Failure to make progress is obviously something different from failure
to deliver, or else the default clause would not provide separately for
both."). The A-12 FSD Contract makes clear that this is a continuing
obligation that exists even though the contract has not yet been funded to
completion.
Third, the authorities cited by Contractors fail to
establish that they were under no contractual duty to make progress.
Contractors rely heavily on an internal government memorandum prepared by the
Defense Department's Contract Finance Committee to support their proposition
that a fixed-price incrementally funded contract imposes no obligations on a
contractor beyond those associated with funding that has already been provided.
The memorandum expresses the committee's view that:
[I]f incremental funding is used, the contractor
cannot be required to expend any effort beyond the Government's limitation of
obligation. Failure to provide additional funding increments not only results
in contract termination, but also makes it necessary to define, after the fact,
what part of the effort should have been completed for the amount of funding actually
provided. Since this division was apparently not possible in the first place,
the contract, for all practical purposes, is converted to a best effort
cost-type vehicle; the Government gets whatever the contractor was able to
complete with the money provided. . . . Any advantages gained from use of a
fixed price R&D contract are at risk until that point when incremental
funding is replaced with full funding.
Memorandum from Chairman, Department of Defense
Contract Finance Committee, to Director, DAR Council 3(c) (June 5, 1992), Joint
Appendix at 68,695 (emphasis added). Setting aside questions about the legal
significance of this memorandum, we conclude that Contractors' duty to make
progress toward completing the A-12 FSD contract is consistent with the views
expressed in the memorandum. Unlike the obligation to complete performance,
which arises only when the contract has been fully funded, Contractors' duty to
make progress is a continuing obligation associated with each payment
installment, and thus is not an "effort beyond the Government's limitation
of obligation." Id.
Having determined that Contractors were obligated to
make enough progress such that contract performance was not endangered, we must
now address what progress Contractors should have made, corresponding to the
funding actually provided by the government, in order to avoid default for
failure to make progress. We disagree with Contractors' argument that it is
"not possible" to answer this question, and that the contract must be
converted into a cost-reimbursement type contract. Id. In litigation over a
contractor's failure to make progress--unlike a dispute over failure to meet a
specific contract requirement or schedule--courts must always determine ex post
the threshold of performance that a contractor must meet to avoid endangering
performance of a contract. See Cibinic & Nash, Administration of Government
Contracts 930-32 (tracing the evolution of the test applied by courts for
failure to make progress). The same is true in this case.
Contractors rely on Electronics of Austin, ASBCA No.
24,912, 86-3 BCA 19,307 (1986), for the proposition that they were under no
duty to make progress. In that case, the Board of Contract Appeals found that
the government had waived the original contract performance schedule and
therefore "there was no time frame within which [the plaintiff] had to
perform." Id. at 97,631. Because there was "no time frame" at
all for performance, the Board held that the plaintiff could not be guilty of
failing to make progress. Id. In the instant case, however, there was a
specified delivery schedule, including the delivery of the first FSD aircraft
in December 1991. See A-12 FSD Contract F, Joint Appendix at 15,049 (initial
delivery schedule for the eight FSD aircraft); Contract Modification P00046
1(b), Joint Appendix at 15,657 (Aug. 17, 1990) (revised delivery schedule).
Therefore, the contract imposed a duty on Contractors to make such progress so
as not to endanger performance as long as the contract was in place, that is,
as long as the contract was being funded. See 48 C.F.R. 52.249-9(a)(1)(ii)
(1984). Consequently, Contractors' protestations to the contrary, we do not
"view the contract that existed prior to full funding as embodying the
'ultimate end item' of the full FSED effort." Reply brief of
Plaintiffs-Cross Appellants at 6. Instead, we hold only that the contract,
throughout its term, embodied a duty to make progress toward the ultimate end
item.
The question of whether Contractors satisfied their
duty is of course that of breach, and must be determined by taking into account
all of the relevant facts and testimony, such as Contractors' statements that
they could not meet the contract specifications, the contract delivery
schedule, nor complete performance at the specified contract price. See supra
Part II.B. We leave it to the trial court to resolve these issues in the first
instance.
CONCLUSION
We reverse the trial court's ruling that the
government's default termination of the A-12 FSD Contract must be converted
into a termination for convenience because the government did not exercise the
necessary discretion. Of course, we do not hold today that the government's
default termination is justified. As Contractors correctly point out, they have
never been found to be in default of the contract. Because the trial court
focused on the legitimacy of the government's default termination decision,
rather than on whether Contractors were in fact in default, the parties have
not yet been afforded the opportunity to fully litigate default. See McDonnell
Douglas Corp. and General Dynamics Corp. v. United States, No. 91-1204C, slip
op. at 2 (Fed. Cl. June 17, 1993). If the government fails to establish at
trial that Contractors were in default under the contract, then the
government's default termination would be improper and Contractors could
rightfully recover damages under the theory of a termination for convenience.
We vacate the trial court's ruling that the government's loss adjustment claim
and Contractors' superior knowledge claim and claim for profits may not be
litigated. Finally, we reject Contractors' argument that the incremental
funding found in the A-12 FSD Contract precludes the government from
terminating the contract for failure to make progress.
REVERSED-IN-PART, VACATED-IN-PART, AND REMANDED.
No. 99-1258
In the Supreme Court of the United States
MCDONNELL DOUGLAS CORPORATION AND
GENERAL DYNAMICS CORPORATION, PETITIONERS
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
SETH P. WAXMAN
Solicitor General
Counsel of Record
WILLIAM B. SCHULTZ
Acting Assistant Attorney
General
MARK B. STERN
THOMAS M. BONDY
Attorneys
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
STEPHEN W. PRESTON
General Counsel
Department of the Navy
Washington, D.C. 20350-0001
QUESTION PRESENTED
Whether the
court of appeals properly reversed and remanded for a trial on the issue of the
contractors' default, where the trial court awarded government contractors a
judgment of $1.2 billion without considering whether they were in default of
the contract.
In the Supreme Court of the United States
No. 99-1258
MCDONNELL DOUGLAS CORPORATION AND
GENERAL DYNAMICS CORPORATION, PETITIONERS
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
OPINIONS BELOW
The opinion of the court of appeals (Pet. App.
1a-27a) is reported at 182 F.3d 1319. The opinion of the Court of Federal
Claims (Pet. App. 28a-72a) is reported at 35 Fed. Cl. 358.
JURISDICTION
The judgment of the court of appeals was entered on
July 1, 1999. A petition for rehearing was denied on October 29, 1999 (Pet.
App. 73a-74a). The petition for a writ of certiorari was filed on January 27,
2000. The jurisdiction of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. In January 1988, a team composed of petitioners
McDonnell Douglas Corporation and General Dynamics Corporation entered into a
contract with the Navy to design and build the A-12 Avenger, a new
carrier-based attack aircraft employing low-observable (stealth) technology.
See Pet. App. 1a-2a. The contract was a fixed-price incentive contract which
provided that petitioners would design and build eight Full Scale Engineering
Development aircraft for a ceiling price of $4,777,330,294. Id. at 2a. Delivery
of the first aircraft was to take place in June 1990, with subsequent
deliveries to be made at specified times from July 1990 to January 1991. Ibid.
From early on, petitioners encountered difficulty
in designing and building an aircraft that would meet critical contract specifications
within the negotiated schedule. Pet. App. 3a. In June 1990, petitioners failed
to deliver the first aircraft as required under the contract, and they informed
the government that the estimated cost of performing under the contract would
substantially exceed the contract ceiling price. Ibid. Petitioners stated at
that time that "the A-12 contractual schedule is not achievable and needs
to be changed," and they asserted that the aircraft performance
specifications had to be "modif[ied]." C.A. App. 15,616.1
In August 1990, after unsuccessfully attempting to
reach agreement with petitioners on an extended date for delivery of the first
aircraft, the Navy unilaterally modified the contract to extend that delivery
date to December 31, 1991. Pet. App. 3a. During the ensuing months, the Navy
and the Department of Defense engaged in a comprehensive review of the issues
arising from the cost, schedule, and performance failures associated with the
program. See C.A. App. 13,388-13,391; Pet. App. 4a. In November 1990,
petitioners submitted a formal proposal to restructure the contract. Pet. App.
4a. Petitioners emphasized that, in their view, development and production of
the A-12 "under the terms of the existing contractual arrangement * * * is
not possible, or equitable, or authorized by law." C.A. App. 16,334A. At
the same time, petitioners commenced efforts to obtain assistance under Pub. L.
No. 85-804, 50 U.S.C. 1431, which authorizes the Secretary of Defense to modify
defense contracts when to do so "would facilitate the national
defense." See C.A. App. 16,329, 18,217-18,226.
On December 17, 1991, the Navy issued a cure notice
informing petitioners that their performance under the contract was
unsatisfactory. Pet. App. 5a. The Navy explained that petitioners had failed to
fabricate sufficient parts to meet the contract schedule. Ibid. In addition,
the Navy stated that petitioners' "failure to meet specification
requirements, such as aircraft weight, jeopardizes the carrier suitability of
your design." C.A. App. 16,524. Because those conditions were
"endangering performance of [the] contract," the Navy informed
petitioners that it might terminate the contract for default unless those
conditions were cured by January 2, 1991. Pet. App. 5a.
In meetings with the government during the next two
weeks, petitioners adhered to the position that they could not build the A-12
for the agreed-upon price, under the agreed-upon schedule, and to the
agreed-upon specifications. See C.A. App. 16,533 (contracting officer's minutes
of Dec. 18 meeting); id. at 16,548- 16,549, 16,554-16,555 (minutes of Dec. 21
meeting); id. at 18,186 (minutes of Jan. 2 meeting); Pet. App. 5a-6a. On
January 2, 1991, in their formal reply to the government's cure notice,
petitioners stated that they would "not meet delivery schedules or certain
specifications of the original contract, or the revised FSD delivery
schedule." Id. at 6a. Petitioners asserted as well that compliance with
the Navy's demand to cure the schedule, weight, and other conditions was
"unachievable." C.A. App. 18,177. Petitioners proposed to have the
government restructure the contract under Pub. L. No. 85-804 as a cost
reimbursement fixed-loss contract, and they agreed to absorb a fixed loss of
$1.5 billion. Pet. App. 6a.
On Saturday, January 5, 1991, Secretary of Defense
Cheney determined that he would not authorize relief from the contract under
Pub. L. No. 85-804. Pet. App. 6a. As he later explained, "no one could
tell me how much the program [would] cost even just through the full-scale
development phase or when [the aircraft] would be available. Data that had been
presented at one point a few months ago turned out to be invalid and
inaccurate." Hearings on Authorization and Oversight of National Defense
Authorization Act For FY 1992 and 1993 Before the House Comm. on Armed
Services, 102d Cong., 1st Sess. 60 (1991). The Secretary's decision was
communicated to the Navy's contracting officer, Rear Admiral William R. Morris,
by Under Secretary of Defense for Acquisition Donald J. Yockey. See Pet. App.
6a-7a. The Under Secretary was aware that the Navy was scheduled to commit $553
million under the contract on January 7, 1991. Id. at 6a. Under Secretary
Yockey informed Admiral Morris that, in light of the Secretary's decision, no
further funds should be obligated. Id. at 7a.
On January 7, 1991, Admiral Morris issued a letter
terminating the A-12 contract for default. Pet. App. 7a. The termination letter
explained that the action was based on the contractors' inability "to
complete the design, development, fabrication, assembly and test of the A-12
aircraft within the contract schedule," as well as their "inability
to deliver an aircraft that meets contract requirements," including the
"weight guaranty contained within the contract specification." C.A.
App. 18,297. The same day, Admiral Morris prepared a termination memorandum for
the file, further explaining that the contractors had demonstrated "an
inability or unwillingness * * * to meet the requirements of the contract."
Id. at 18,303. The memorandum concluded that "the team's failure to make
progress and to deliver an aircraft meeting required [cost, performance, and
schedule specifications] has placed the entire program in jeopardy; and the
contractors have offered no adequate excuse for these failures." Id. at
18,305. Shortly thereafter, the Navy issued a formal demand for the return of
unliquidated progress payments totaling $1.35 billion. Pet. App. 7a.
2. In June 1991, petitioners filed the present
action in the Claims Court (now the Court of Federal Claims (CFC)) challenging
the government's default termination on a number of grounds. Pet. App. 7a. The
complaint requested (inter alia) that the court "convert the government's
termination for default into a termination for convenience." Ibid.2 The
CFC eventually focused on Count XVII of the complaint, which claimed that the
government's termination of the contract for default was improper because the
actions of the Department of Defense had deprived the contracting officer of the
ability to make an "independent decision" regarding the termination.
C.A. App. 68,460. The court held a trial on Count XVII in September 1993. The
court made clear at the outset that the purpose of the trial was not to
consider "whether there was sufficient evidence to justify a legitimate
decision to terminate this contract for default," but solely to determine
"whether improper factors [led] to the decision such that the decision
itself was made for a[n] illegitimate reason." Id. at 74.
In December 1994, the CFC issued a brief order
vacating the default termination. See Pet. App. 29a. In April 1996, the court
issued findings of fact and conclusions of law in support of its decision to
convert the government's termination for default to a termination for convenience.
Id. at 28a-72a.3 The court acknowledged that petitioners had not met the June
1990 delivery date for the first plane, and had informed the Secretary of
Defense that they "were having schedule and cost problems that would not
allow them to perform under the terms of the contract." Id. at 33a. The
court also found that Admiral Morris, the contracting officer, had "based
the termination on the fault of the contractors because he did not believe that
the Navy bore any responsibility for the contractors' perceived inability to
achieve the contract specifications or deliver the aircraft on schedule,"
and because a termination of the contract for convenience "would result in
a windfall to the contractors." Id. at 47a.
Relying principally on the decision of the United
States Court of Claims (a predecessor to the Federal Circuit) in Schlesinger v.
United States, 390 F.2d 702 (1968), the CFC nevertheless concluded that the
default termination was improper because it was not the product of
"reasoned discretion." Pet. App. 51a. The court found that Secretary
Cheney's decision not to grant relief under Pub. L. No. 85-804, which led to
the termination of the A-12 program, was at odds with the Navy's inclination to
continue the contract despite petitioners' failings. Id. at 52a-54a. On that
basis, the court concluded that "[t]he A-12 contract was not terminated
because of contractor default," but "because the Office of the
Secretary of Defense withdrew support and funding from the A-12." Id. at 72a.
After converting the government's termination for
default to a termination for convenience, the CFC held further proceedings on
the question of damages and ultimately entered judgment for petitioners in the
amount of $3,877,767,376. Pet. App. 2a. Because petitioners had already
received progress payments of nearly $2.7 billion, the net judgment awarded by
the trial court was approximately $1.2 billion, plus interest. Id. at 8a.
3. The court of appeals reversed and remanded for a
trial on the question whether petitioners were in default of the contract. See
Pet. App. 1a-27a. The court ruled that the CFC had "erred by vacating the
termination for default without first determining whether a default
existed." Id. at 18a. The court noted that on remand the government will
bear the burden of proof with respect to the question whether termination for
default was justified, and that "if the government is not able to make
this showing, then the default termination was invalid and [petitioners] would
be entitled to a suitable recovery." Id. at 19a.
The court of appeals concluded that Schlesinger was
inapposite. It explained that "[t]he illegality in Schlesinger stemmed
from the Navy's reliance on contractor default as a pretext to terminate its
relationship with the contractor, independent of the state of actual
performance under the contract." Pet. App. 11a. In the instant case, by
contrast, the court of appeals found that "the record demonstrates that
the government properly terminated the A-12 program [and contract] for reasons
related to contract performance." Id. at 14a. The court concluded that
"because the termination for default was predicated on contract-related
issues, it was within the discretion of the government." Id. at 2a.4
ARGUMENT
The court of appeals' interlocutory ruling is
correct and does not conflict with any decision of this Court or any other
court of appeals. Further review is not warranted.
1. a. Petitioners do not contend that the decision
of the court of appeals is in conflict with any decision of this Court or of
any other court of appeals. Instead, their core contention is that the court of
appeals did not properly apply the rationale of Schlesinger v. United States,
390 F.2d 702 (Ct. Cl. 1968), which is the authority upon which the trial court
placed primary reliance. See Pet. 11; Pet. App. 51a-59a. Petitioners' claim of
an intra-circuit conflict does not satisfy the Court's usual criteria for the
exercise of certiorari jurisdiction. See Wisniewski v. United States, 353 U.S.
901, 902 (1957).
b. The interlocutory nature of the court of
appeals' ruling also weighs against review by this Court at the present time.
The court of appeals "remand[ed] the case to the trial court for a
determination of whether the government's default termination was justified, an
issue upon which [the court of appeals] express[ed] or intimate[d] no
view." Pet. App. 2a. Review by this Court would consequently be premature.
See, e.g., Brotherhood of Locomotive Firemen v. Bangor & Aroostook R.R.,
389 U.S. 327, 328 (1967) ("because the Court of Appeals remanded the case,
it is not yet ripe for review by this Court"); Virginia Military Inst. v.
United States, 508 U.S. 946 (1993) (the Court "generally await[s] final
judgment in the lower courts before exercising [its] certiorari jurisdiction")
(Scalia, J., respecting the denial of certiorari).
2. a. The decision of the court of appeals is
correct and consistent with that court's precedent. In Schlesinger, the Navy
terminated a contract for 50,000 caps on grounds of default when the contractor
sought a limited extension of a delivery date. See 390 F.2d at 703-706. The
court of appeals agreed that Schlesinger was technically in default at the time
of the termination because he had failed to deliver 15,000 of the caps by a
date specified in the contract. Id. at 706-707. Based on the evidence
introduced at trial, however, the court determined that the Navy had terminated
the contract because the chairman of a congressional subcommittee had sent the
Navy a letter implying that the contract should be canceled for reasons
unrelated to the failure to supply the caps on time. See id. at 705, 708 &
n.6.
The Court of Claims held that under those
circumstances, the termination for default should be treated as a termination
for convenience. See 390 F.2d at 707-710. The court found that the Navy had not
exercised its discretion to terminate the contract, but had "simply
surrendered its power of choice" in light of congressional pressure. Id.
at 708. The court explained that the contractor's "status of technical
default served only as a useful pretext for the taking of action felt to be
necessary on other grounds unrelated to the plaintiff's performance." Id.
at 709.
The holding in Schlesinger has no application here.
As the court of appeals observed, "Schlesinger and its progeny merely
stand for the proposition that a termination for default that is unrelated to
contract performance is arbitrary and capricious, and thus an abuse of the
contracting officer's discretion. This proposition itself is but part of the
well established law governing abuse of discretion by a contracting
official." Pet. App. 13a.5 Petitioners do not and could not plausibly
contend that the A-12 contract was terminated for reasons unrelated to
performance. Rather, "[t]he record shows that the government's default
termination was not pretextual or unrelated to Contractors' alleged inability
to fulfill their obligations under the contract." Ibid. Indeed,
petitioners' acknowledged inability to perform triggered the Secretary's review
and was the impetus for the actions taken by the Office of the Secretary of
Defense and the contracting officer. See id. at 3a-7a. Nor were petitioners'
failures to satisfy the contract terms merely "technical"
(Schlesinger, 390 F.2d at 709): petitioners affirmatively declared that they
could not meet the contract's basic cost, schedule, or performance
specifications. See Pet. App. 3a-6a.
b. In this Court, petitioners do not contend that
the government's termination of the A-12 contract for default was a "pretext"
(Schlesinger, 390 F.2d at 709); nor do they assert that their admitted
inability to satisfy the critical cost, schedule, and performance provisions of
the agreement reflected shortcomings that are "technical" (ibid.) in
nature. Petitioners urge instead that they were deprived of "a reasoned
determination on the merits as to whether a default termination was justified,
including consideration prior to termination of any reasons or excuses for
problems in performance." Pet. 6. Petitioners thus contend that if a
contracting officer fails adequately to consider a contractor's proffered
excuses for non-performance, the government's termination for default may be
converted to a termination for convenience, even if the failures of performance
go to the heart of the contract, and even if the contractor in fact has no
valid excuse for those failures. Petitioners do not identify any provision of
law that would authorize a court to grant such relief on that basis, nor do
they cite any judicial decision that has adopted their legal theory.
In any event, petitioners' claim is factually
unsupported. On the day the contract was terminated, the contracting officer
issued a letter, and prepared a memorandum to the file, setting forth the
reasons for the termination. C.A. App. 18,297, 18,303; see Pet. App. 7a.
Contrary to petitioners' suggestions (see, e.g., Pet. 14), Admiral Morris
considered and rejected petitioners' proffered excuses for their performance
failures. As Admiral Morris testified, he spent "60 to 70 percent of
December [1990], through the 7th of January [1991], working [on] A-12
issues," and took part in "dozens" of meetings and
conversations, C.A. App. 3791, which set out the contractors' excuses in
detail. His termination memorandum concluded that "the contractors have
offered no adequate excuse for [their] failures." Id. at 18,305.6 Indeed,
the CFC itself recognized that
Admiral Morris based the termination on the fault
of the contractors because he did not believe that the Navy bore any
responsibility for the contractors' perceived inability to achieve the contract
specifications or deliver the aircraft on schedule. Absent some fault on the
part of the Navy, he believed that he could not terminate for convenience
because he believed that action would result in a windfall to the contractors.
Pet. App. 47a.
c. A court is not, of course, required to accept
the contracting officer's default termination. Indeed, the contracting
officer's decision receives no presumption of correctness in an action
challenging a termination of a government contract for default. See Wilner v.
United States, 24 F.3d 1397, 1401-1402 (Fed. Cir. 1994) (en banc). The question
in this case is simply whether that inquiry may be pretermitted altogether,
leaving petitioners in the position they would have occupied had no default
occurred. As the court of appeals in this case correctly held, "the trial
court erred by vacating the termination for default without first determining
whether a default existed." Pet. App. 18a. That holding does not warrant
this Court's review, especially in the present interlocutory posture of this
case.
CONCLUSION
The petition for a writ of certiorari should be
denied.
Respectfully submitted.
SETH P. WAXMAN
Solicitor General
WILLIAM B. SCHULTZ
Acting Assistant Attorney
General
MARK B. STERN
THOMAS M. BONDY
Attorneys
STEPHEN W. PRESTON
General Counsel
Department of the Navy
MARCH 2000
1 Petitioners' statements were made in the midst of
increasing evidence of their failure to overcome a wide range of problems in
the design and fabrication of the aircraft. For example, the Navy estimated
that the first plane entering fleet operations would weigh nearly 8,000
pounds-or over 20 percent-more than the empty weight specified in petitioners'
best and final contract offer. See Pet. App. 32a; C.A. App. 27,080. In
addition, petitioners had been unable successfully to fabricate (much less
assemble) the large composite parts necessary to produce the aircraft's inner
wing, and were more than a year behind in completing the avionics software. See
C.A. App. 3402-3404, 3519-3528, 3736-3738, 13,691, 25,906, 26,549-26,550.
2 "The right to terminate a contract when
there has been no fault or breach by the non-governmental party, that is, for
the 'convenience' of the government, appeared as a legal concept after the
Civil War, to facilitate putting a speedy end to war production." Maxima
Corp. v. United States, 847 F.2d 1549, 1552 (Fed. Cir. 1988). When the contract
is properly terminated for convenience, the contractor's recovery is limited to
"costs incurred, profit on work done and the costs of preparing the
termination settlement proposal. Recovery of anticipated profit is
precluded." Ibid. If the contractor would have sustained a financial loss
in completing the contract, the contractor's recovery is further reduced by the
rate of loss that the contractor was experiencing. 48 C.F.R. 49.203. Where a
contract has been terminated because of an erroneous determination that the
contractor was in default, the Federal Circuit has recognized that it has the
power to treat the termination as one for the convenience of the government.
See Maxima Corp., 847 F.2d at 1553.
3 During the period between the December 1994 order
and the April 1996 opinion, the CFC repeatedly rejected the government's
contention that the termination for default could not properly be converted to
a termination for convenience without a trial to determine whether petitioners
were, in fact, in default. The court refused to allow the government to file a two-volume
proffer detailing the evidence of the contractors' default. C.A. App. 177, 263.
The court eventually held a trial, in 1995, to consider only the evidence of
default that was concealed from the Navy. But the court stopped those
proceedings in the middle of the government's case, concluding that it had
"heard no credible evidence that the Navy was unaware of critical
information at the time of termination." Id. at 179.
4 The court of appeals noted the government's
separate arguments concerning the trial court's assessment of damages. Pet.
App. 19a-20a. It concluded, however, that in light of its disposition of the
liability issue, questions pertaining to damages were "not ripe for [its]
decision" and should be considered in the first instance by the CFC on
remand. Id. at 20a. The court also rejected the contention raised in
petitioners' cross-appeal that the A-12 contract was not subject to termination
for default because it was funded incrementally. Id. at 21a-26a. Those issues
are not raised in the petition.
5 As the court of appeals correctly noted (Pet.
App. 11a-12a), the two other cases on which petitioners principally rely are in
the same mold as Schlesinger and reflect the same principle. In Darwin
Construction Co. v. United States, 811 F.2d 593 (Fed. Cir. 1987), the court
held that the government's termination for default was arbitrary and capricious
because the "action was taken solely to rid the Navy of having to deal
with" the contractor. Id. at 596. The court stated that "[t]he facts
of the case before us are almost identical to the salient facts in Schlesinger,
where it was found that the contractor's status of technical default served
only 'as a useful pretext for taking the action found necessary on other
grounds unrelated to the plaintiff's performance.'" Ibid. (quoting
Schlesinger, 390 F.2d at 709). Similarly in John A. Johnson Contracting Corp.
v. United States, 132 F. Supp. 698 (Ct. Cl. 1955), the court held that the
government's termination for default should be treated as a termination for
convenience, on the ground that the contracting officer's "action in
terminating the [contract] for delay did not represent his judgment as to the
merits of the case, but was a device to satisfy what lawyers told him were, or
probably were, the legal requirements of the situation." Id. at 705.
6 Contrary to petitioners' suggestions (see Pet.
11-12, 14), Admiral Morris's termination memorandum addressed all but one of
the factors identified in the pertinent provision of the Federal Acquisition
Regulation (FAR), 48 C.F.R. 49.402-3(f). See C.A. App. 18,302-18,306. The only
factor that the memorandum did not mention-"[t]he urgency of the need
for" the A-12 (see Pet. App. 49a)-was obvious to all, and had in fact been
considered. See C.A. App. 1047, 1070, 1155, 1264, 1274, 1315. See also DCX,
Inc. v. Perry, 79 F.3d 132, 135 (Fed. Cir.) (noting that the FAR "does not
confer rights on a defaulting contractor" and that consideration of the
FAR factors is not a "prerequisite[] to a valid termination"), cert. denied,
519 U.S. 992 (1996).